POST-APPOINTMENT
AWARD
BIM
EXECUTION PLAN TEMPLATE
(WORK
ACCORDING TO ISO 19650)
PROJECT |
|
ORIGINATOR |
|
VOLUME/ SYSTEM |
|
LEVELS &LOCATION |
|
TYPE |
|
FUNCTION |
|
NUMBER |
XXXXXX |
- |
XXXXXX |
- |
XX |
- |
XX |
- |
XXX |
- |
XX |
- |
000XXX |
Table 0‑1: BEP Document Code
? This document is owned and maintained by the current Project Delivery Manager listed below.
Project
Delivery Manager Name |
Company
Name |
Project
Contract |
Contract
No |
Function |
e-mail |
BEP
Version |
|
|
|
|
|
|
R-1.0 |
|
|
|
|
|
|
R-1.1 |
|
|
|
|
|
|
R-2.0 |
|
|
|
|
|
|
R-.. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 0‑2: Project Delivery Manager
? This project plan has been agreed by the representatives of the project team as listed below with the authority of their parent companies to accept this document as the Agreed BIM Execution Plan. By signature below, this BIM Execution Plan is herewith adopted and incorporated into the Agreement, dated ..../../.., for .......................... between ....................................and ...............................................
PARTY/DISCIPLINE |
REPRESENTATIVE NAME/SURNAME |
SIGN |
DATE |
APPOINTING
PARTY |
|
|
|
ARCHITECT |
|
|
|
GENERAL
CONTRACTOR |
|
|
|
STRUCTURAL
ENGINEER |
|
|
|
MECHANICAL
ENGINEER |
|
|
|
PLUMBING
ENGINEER |
|
|
|
ELECTRICAL
ENGINEER |
|
|
|
LANDSCAPE
ARCHITECT |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 0‑3:Document Authority
? The information contained in this
document has been prepared with the understanding that this is a live document
and will require periodic updates throughout the duration of the project to
reflect the progress of the project (major revisions before each major phase)
and incorporate newly agreed procedures and workflows. Initial authorship by .......................... in 2019.
þ "Rev 1.0" is the first major release of the document.
þ Following major releases will be
"2.0", "3.0" etc.
þ "Rev. 0.1" is the first
iteration of the document.
þ For each minor change to the
document, the decimal revision numbers to indicate the status of the current
update process (1.1, 1.2, 2.1 etc.).)
will be used,
þ Revisions starting with 0 (e.g. 0.1,
0.2) are draft issues for comment. Documents with a "0" revision
number have not formally been issued.
? This document is made available to
the ................ on the express understanding that the information obtained
in it will be regarded and treated by the .............., their contractors and
their sub-contractors on their BIM projects as
strictly confidential. The contents of this document are
intended only for the sole purpose and use of ..........., their contractors
and their sub-contractors on their BIM projects
and not to be distributed to any other person outside the scope of this
document.
REVISION |
DATE |
PREPARED BY |
REVIEWED BY |
APPROVED BY |
ISSUED TO |
R-0.1 |
..../../.. |
|
|
|
|
R-1.0 |
..../../.. |
|
|
|
|
R-1.1 |
..../../.. |
|
|
|
|
R-2.0 |
..../../.. |
|
|
|
|
Table 0‑4: Document Revision Tracking
DOCUMENT CHANGE LOG |
||
REVISION |
SECTION |
DESCRIPTION |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 0‑5: Document Change
Log
DOCUMENT CONTROL / DOCUMENT REVISION TRACKING
1.3 PROJECT INFORMATION (PIT_2)
1.4 MAJOR PHASES OR MILESTONES /
BRIEF SCHEDULE
2 INFORMATION MANAGEMENT INDIVIDUALS
2.1 FUNCTIONS RESPONSIBILITIES &
AUTHORITIES (INDIVIDUALS LIST)-FRA_2
2.2 INFORMATION MANAGEMENT
ASSIGNMENT MATRIX (REM-A_3)
3 UPDATED REQUESTS & INFORMATION
FROM INVITATION TO TENDER & TENDER RESPONSE PACKAGES
3.1 APPOINTING PARTY'S EXCHANGE
INFORMATION REQUIREMENTS
3.1.1 APPOINTING PARTY'S INFORMATION
REQUIREMENTS (INCL. UPDATES)
3.1.1.1.1 BIM GOALS (CONDITIONS of
STATISFACTION-CoS) / BIM OBJECTIVES
3.1.1.3 THE INTENDED PROCUREMENT ROUTE
(PRS_2)
3.1.1.4 PLAIN/PRE-QUALIFICATION QUESTIONS
(PLQ_1)
3.1.2 LEVEL OF INFORMATION NEED
MANUAL (LOIN_2)
3.1.3 SUPPORTING INFORMATION FOR
LEAP(SUP-LEAP_1)
3.2 REFERENCE INFORMATION &
SHARED RESOURCES (REF_2)
3.2.1 LIBRARY GUIDE & LIBRARY
STRUCTURE IN DATA ENVIRONMENT (LIB_2).
3.2.2 SHARED RESOURCES GUIDE &
SHARED RESOURCES IN DATA ENVIRONMENT (SHR_2)
3.2.3 PROJECT’S REFERENCE INFORMATION
AND SHARED RESOURCES (REF_2)
3.3 PROJECT'S INFORMATION PROTOCOL
RELATED REQUIREMENTS
3.3.1 PROJECT'S COMMON DATA
ENVIRONMENT STANDARDS, METHODS & PROCEDURES (CDE_2)
3.3.2 TRAINING REQUIREMENTS (TRA_1)
4 INFORMATION STANDARD (ýns_2)
4.1 INFORMATION CONTAINER NAMING REQUIREMENTS (ICN_2)
4.1.2 ORIGINATOR (DESIGN PHASES)
DESIGNATORS
4.1.7 SHEET/SUBMITTAL
DESCRIPTION-VIEW-WORKSET NAMINGS
4.2 MEANS OF STRUCTURING & CLASSIFYING INFORMATION
4.2.1 PROJECT'S CLASSIFICATION SYSTEM
(CLM_1)
4.3.2 INFORMATION EXCHANGE /
ATTRIBUTE DATA
4.3.2.1 PROJECT'S CONSTRUCTION OPERATIONS
BUILDING INFORMATION EXCHANGE (COBIE) STANDARDS
4.3.2.2 INFORMATION TO BE EITHER EXCLUDED
from OR INCLUDED ýn INFORMATION MODELS.
4.3.2.3 PROJECT'S IFC & mvd STANDARDS
4.3.2.4 THE EXCHANGE OF INFORMATION WITHIN
THE APPOINTING PARTY’S ORGANIZATION
4.3.2.5 THE EXCHANGE OF INFORMATION BETWEEN
THE APPOINTING PARTY AND EXTERNAL STAKEHOLDERS
4.3.2.8 THE EXCHANGE OF INFORMATION BETWEEN
PROSPECTIVE APPOINTED PARTIES ON THE SAME PROJECT
4.3.2.9 THE EXCHANGE OF INFORMATION BETWEEN
INTERDEPENDENT PROJECTS
4.4 METHOD OF ASSIGNMENT FOR LEVEL OF INFORMATION NEED
4.5 UNITS, MEASUREMENT &
COORDINATE SYSTEM
4.7.1 SHEET ORGANIZATION & SIZES
4.8 ANNOTATIONS, DIMENSIONS, LINES,
SCHEDULES, ABBREVIATIONS AND SYMBOLS
4.9 COLLABORATION & MODELING
& PUBLISHING STANDARDS (WITHIN THE CDE) (COL-S_2)
4.10 USE OF INFORMATION DURING THE OPERATIONAL PHASE OF THE ASSET
4.10.1 PIM TO AIM STANDARDS (pat-s)
5 INFORMATION PRODUCTION METHODS and
PROCEDURES (pmp_2)
5.1 SPATIAL COORDINATION
(COORDINATES&GEO-LOCATION) METHODS & PROCEDURES (SCO_2)
5.1.1 PIM ORIGIN & ORIENTATION
5.2 FEDERATION STRATEGY &
INFORMATION CONTAINER BREAKDOWN STRUCTURE (FSB_1)
5.3 THE CAPTURE OF EXISTING ASSET
INFORMATION
5.3.2 QUANTITY EXTRACTION &
TRACKING STRATEGY
5.4 THE SECURITY OR DISTRIBUTION OF
INFORMATIOn
5.4.1 SECURITY REQUIREMENTS (SCR_1)
5.5 THE GENERATION, REVIEW OR
APPROVAL OF NEW INFORMATION
5.5.1 COLLABORATION & MODELLING
& publýshýng METHODS & PROCEDURES (WITHIN THE CDE) (COL-mP_2)
5.5.1.1 COLLABORATIVE WORKSPACE
5.5.1.2 MODELLING (PROCESS/WORKFLOW)
METHODS & procedures (wýthýn cde).
5.5.1.3 PROJECT'S IFC & mvd METHODS
& PROCEDURES
5.5.1.5 COMMUNICATION PROCEDURES (WITHIN
CDE)
5.5.1.5.1 ELECTRONIC COMMUNICATION PROCEDURES
5.5.1.5.2 MEETING COMMUNICATION PROCEDURES
5.5.1.6 PUBLISHING METHODs & PROCEDURES
5.5.1.8 DATA MANAGEMENT ACCORDING TO
SEGREGATION (DAS_2)
5.5.2 QUALITY ASSURANCE MANUAL
(QUA_3)
5.5.2.2 QUALITY ASSURANCE (QA)
5.5.3 COORDINATION, CLASH DETECTION
& ISSUE MANAGEMENT MANUAL (CCI_3).
5.6 CDM/HEALTH & SAFETY
REQUIREMENTS (CDM)
5.7 PIM TO AIM TRANSITION METHODS
AND PROCEDURES (PAT-MP_1)
5.7.1 PROJECT'S CONSTRUCTION
OPERATIONS BUILDING INFORMATION EXCHANGE (COBIE) METHODS & PROCEDURES
5.8 THE DELIVERY OF INFORMATION TO
THE APPOINTING PARTY
6 INFORMATION DELIVERY STRATEGY
(dt-ýds_1)
6.1 APPOINTMENT RELATED REQUIREMENTS
6.2 TENDER RESPONSE REQUIREMENTS
& EVALUATION CRITERIA (TEN-CR
6.2.1 RISK ASSESSMENT REQUIREMENTS
(RAS_1)
6.2.1.1 KEY PERFORMANCE INDICATORs (KPIS)
6.2.2 ACCEPTANCE CRITERIA MANUAL
(ACR_1)
6.3 TASK TEAMS' CAPABILITY &
CAPACITY
6.3.1 CAPABILITY AND CAPACITY
ASSESSMENT OF TASK TEAMs (TT-CCA_1)
6.3.1.1 INFORMATION MANAGEMENT CAPABILITY
AND CAPACITY ASSESSMENT FORM (CCA_IM).
6.3.1.2 INFORMATION PRODUCTION CAPABILITY
AND CAPACITY ASSESSMENT FORM (CCA_IP).
6.3.1.3 IT-INFORMATION TECHNOLOGY
CAPABILITY AND CAPACITY ASSESSMENT FORM (CCA_IT)
6.3.2 TASK TEAMS' INFORMATION
DELIVERY STRATEGIES (TT-IDS_1)
6.4 DELIVERY TEAM'S CAPABILITY &
CAPACITY (DTCC_1)
6.5 DELIVERY TEAM'S MOBILIZATION
PLAN
6.6 DELIVERY TEAM'S RISK REGISTER
(drr_1)
6.7 INFORMATION DELIVERY STRATEGY
(DT-IDS_1)
7 HIGH LEVEL RESPONSIBILITY MATRIX
(HLRM_1)
7.1 DETAILED RESPONSIBILITY MATRIX
(DRM_0)
7.2 TASK INFORMATION DELIVERY PLAN
(TIDP_1...N)
7.3 MASTER INFORMATION DELIVERY PLAN
(mýdp_0)
8 SCHEDULE OF SOFTWARE, HARDWARE
& IT INFRASTRUCTURE (SCH-IT_1)
8.2 HARDWARE & IT INFRASTRUCTURE
8.3 SCHEDULE OF SOFTWARE, HARDWARE
& IT INFRASTRUCTURE
9 TEMPLATES FOR FURTHER DELIVERY
PHASE ACTIVITIES (4.2 - 5.8)
9.1 LEAD APPOINTED PARTY'S EXCHANGE
INFORMATION REQUIREMENTS (EIR-LEAP)
9.3 MOBILIZATION OF INFORMATION
TECHNOLOGY
9.4 PROJECT'S INFORMATION PRODUCTION
METHODS AND PROCEDURES TEST
9.5 CHECKING TASK TEAM'S
AVAILABILITY OF REFERENCE INFORMATION AND SHARED RESOURCES
9.6 TASK TEAM'S QUALITY ASSURANCE
CHECK
9.7 TASK TEAM'S INFORMATION REVIEW
& APPROVAL (BY TASK TEAM) FOR SHARING
9.8 DELIVERY TEAM'S INFORMATION
REVIEW FOR COORDINATION
9.9 REVIEW & AUTHORIZATION OF
THE INFORMATION MODEL BY LEAD APPOINTED PARTY
9.11 INFORMATION MODEL REVIEW & ACCEPTION
BY APPOINTING PARTY
10 TEMPLATES FOR OPERATIONAL PHASE
ACTIVITIES
11 REFERENCE DOCUMENTS &
STANDARDS
Annex_2.1 = REM-A_3: Information Management Assignment
Matrix
Appendix_3.1
= OIR: Organizational Information
Requirements
Appendix_3.2
= AIR: Asset Information Requirements
Annex_3.3
= USE_2: BIM USE MATRIX
Annex_3.4
= BUA_2: BIM USE ANALYSIS
Appendix_3.5
= PLQ_1 : Plain/Pre-Qualification Questions
Annex_3.6
= LOIN_2: Level of Information Need Manual
Appendix_3.7
= PoW-1: Plan of Work (with Milestones
& Dates)
Appendix_3.8
= INP_2: Project’s Information Protocol
Annex_4.1
= ATD: Attribute Data Log
Annex_5.1
= CHL: Change Log Template
Annex_5.2
= CLAM: Clash Detection Matrix
Annex_6.1
= ACR_1: Acceptance Criteria Manual
Annex_6.2
= CCA_IM: Information Management Capability
and Capacity Assessment Form
Annex_6.3
= CCA_IP: Information Production
Capability and Capacity Assessment Form
Annex_6.4
= CCA_IT: Information Technology Capability and Capacity Assessment Form
Appendix_6.5
= MOB_1: DELIVERY TEAM'S MOBILIZATION
PLAN
Appendix_6.6
= IDM: INFORMATION DELIVERY MANUAL
Annex_7.1
= HLRM_1: Delivery team’s High Level
Responsibility Matrix
Annex_7.2
= DRM_0: Delivery Team’s Detailed
Responsibility Matrix Initial Version (Template)
Annex_7.3
= TIDP-TMP: Task Information Delivery
Plan Template
Annex_7.4
= MIDP_0: Master Information Delivery
Plan Initial Version (Template)
Appendix_9.1
= EIR-LEAP-TMP: Lead Appointed Party's Exchange Information Requirements
Template
Appendix_9.2
= MORE-TMP: Mobilization of Resources
Report Template
Appendix_9.3
= MOIR-TMP: Mobilization of
Information Technology Report Template
Appendix_9.5
= CR-TT-TMP: Task Team's Access Check
Report Template
Appendix_9.6
= QUA-TT-TMP: Task Team's Quality
Assurance Check Report Template
Appendix_9.7
= IRR-TT-TMP: Task Team's Information
Review (by Task Team) Report Template
Appendix_9.8
= IMR-DT-TMP: Delivery Team's
Information Model Review Report Template
Appendix_9.9
= TTS-RR-TMP: Task Teams' Submittals
& PIM Review Report by Leap Template
Appendix_9.10
= SBL-TMP: Submittal Lists Template
Appendix_9.11
= PIM-RR-TMP: Appointing Party's PIM
Review Report Template
Appendix_9.12
= PAR-TMP: PIM to AIM Requirements
Template
Appendix_9.13
= CLL-TMP: Capture Lessons Learned
Template (for LEAP and APP's Use)
Appendix_9.14
= RLL-TMP: Lessons Learned Register
Template(by APOP)
Table 0‑2:
Project Delivery Manager
Table 0‑4: Document
Revision Tracking
Table 0‑5: Document
Change Log
Table 1‑1:Project
Information Table (PIT_1)
Table 1‑2:
Major Milestones/Brief Schedule Table
Table 1‑3: BEP
versions as per project phases list
Table 2‑1: (FRA_2)
Functions Responsibilities & Authorities (Individuals List)
Table 3‑1: BIM
Goals / BIM Objectives
Table 3‑2: BIM USES ACROSS PROJECT PHASES
Table 3‑3: PRS
_2: Procurement Route (Schema & Table)
Table 3‑4: Level
of Information Need Classification Table (as per BIM Uses)
Table 3‑5: Supporting
Information List (incl. Location).
Table 3‑7: Shared Resources Folder
Table 3‑8: REF_1:
Project’s reference information and shared resources
Table 3‑9: EXAMPLE
OF AN INFORMATION CONTAINER DEVELOPMENT IN CDE (AS A GUIDE)
Table 4‑1: FILE, & SHEET CODE /FILE (FOR
PUBLICATION OF THE SHEET) NAME
Table 4‑2: Project
Designators
Table 4‑3: Originator
(Design Phases) Designators
Table 4‑4: Zone
& Sub-Zone Designators
Table 4‑6: File
Type Designators
Table 4‑7: Discipline
Designators (Excluding MEP)
Table 4‑8: Discipline
Designators (MEP)
Table 4‑12:Project's
Classification System
Table 4‑14: Status
codes for information containers within the CDE
Table 4‑15: Metadata Assignment
Table 4‑16: Application
of Status Codes
Table 4‑17: Model
Description Document Template
Table 4‑18: Exchange
Formats Table
Table 4‑20: Classification and COBie
Table 4‑21: Information
to be excluded from or included in information models table
Table 4‑22: Project's
IFC Standards Table
Table 4‑23: Main
MVDs of The Project
Table 4‑24: Method
of assignment for Level of Information Need Table
Table 4‑25: Units
and Measurement
Table 4‑26: Level
of Accuracy Table (LOA)
Table 5‑1: Coordinates
and Geo-Location Table (SCO)
Table 5‑2:Federation
Parts List (Sample)
Table 5‑4: Security
& Extranet Access, Distribution
Authority
Table 5‑5: BIM Test Mock-Ups Table
Table 6‑1: Appointment
Document RACI Table
Table 6‑2: (KPIS)
Key Performance Indicators
Table 8‑1: (SCH-IT_1)
Schedule of Software, Hardware & IT
Figure 3‑2: CDE concept in
ISO 19650-1
Figure 3‑3: Revision
control during Work in Progress (WIP)
Figure 3‑4: Revision
control of Shared information
Figure 3‑5: Revision
control of Published information containers
Figure 3‑6: Figure
of the schema illustrating the development process mentioned in Table 3.9
Figure 3‑7: Project's Folder Structure in Cloud
Figure 3‑8: Project's Folder Structure in local
servers of the actor
Figure 4‑1: Process Map - Exchange of Information Between within the Apop's Organization
Figure 4‑2: Process Map - Exchange of Information Between the Apop and External Stakeholders
Figure 4‑3: Process Map - Exchange of Information Between Apop and External Operators or
Maintainers
Figure 4‑4: Process Map - Exchange of Information Between Peap and the App
Figure 4‑5: Process Map - Exchange of Information Between PEAPs on the Same Project
Figure 4‑6: Process Map - Exchange of Information Between Independent Projects
Figure 5‑1: PIM
Origin & Orientation
Figure 5‑2: Information
Container Breakdown of the Federation Strategy
Figure 5‑3: Quantity
extraction & tracking strategy.
Figure 5‑4:
Modelling Process/Workflow Schema.
Figure 6‑1: Project's
Brief Process Map
?
Purpose of this BEP document.
.....
v APOP: APPOINTING PARTY
v LEAP: LEAD APPOINTED PARTY
v PEAP: PROSPECTIVE LEAD APPOINTED PARTY
v APP: APPOINTED PARTY
v ...
v ...
v
I
Ref.to ISO-19650-2/5.1.6,
5.2.2
Project Name |
.......... |
Asset Owner |
.......... |
Project Owner/ Client |
.......... |
Appointing Party |
.......... |
Project Location and Address |
.......... |
Project Code/Number(s) |
.......... |
Contract Type / Delivery
Method |
.......... |
Brief Project Description |
.......... |
Additional Project Description |
.......... |
Asset Type |
.......... |
Asset Structure |
.......... |
Design Start Date |
.......... |
Construction Start Date |
.......... |
Handover Date |
.......... |
Estimated Asset Area (Gross) |
.......... |
Estimated Asset Area (Net) |
.......... |
Estimated Asset Value |
.......... |
.......... |
.......... |
.......... |
.......... |
.......... |
.......... |
.......... |
.......... |
.......... |
.......... |
Table 1‑1:Project Information Table (PIT_1)
?
Only major phases and/or milestones will be mentioned.
OMNICLASS |
CODE |
DEFINITION |
START DATE |
FINISH DATE |
STATUS- Ended/Started |
|
PREPARATION |
31-10 00 00 |
A |
Appraisal / |
- |
- |
|
31-20 00 00 |
B |
Design Brief/ |
- |
- |
||
DESIGN |
31-30 00 00 |
C |
Schematic Design |
- |
- |
|
31-40 00 00 |
D |
Design Development |
- |
- |
|
|
E |
Technical Design |
- |
- |
|
||
PRE-CONSTRUCTION |
31-50 00 00 |
F1 |
Production Information- |
- |
- |
|
F2-5 |
Production Information- |
- |
- |
|
||
F6-G |
Tender Documentation |
- |
- |
|
||
H |
Tender Action |
- |
- |
|
||
CONSTRUCTION |
31-60 00 00 |
J |
Mobilization |
- |
- |
|
K1 |
Shop Drawing Phase-Start (In
line with executions) |
- |
- |
|
||
K2 |
Construction Start |
- |
- |
|
||
K3 |
Construction Works |
- |
- |
|
||
K4 |
Substantial Completion |
- |
- |
|
||
K5 |
Construction |
- |
- |
|
||
HANDOVER/ |
31-70 00 00 Handover / Closeout |
K6-7 |
Handover / Close-out , |
- |
- |
|
OPERATIONS |
31-80 00 00 Operations |
L |
USE-Post Practical |
- |
N/A |
|
M |
R&D-Model Maintenance |
N/A |
N/A |
|
||
CLOSE-OUT |
31-90 00 00 Closure |
Z |
Demolition |
N/A |
N/A |
|
Table 1‑2: Major Milestones/Brief Schedule Table
I
BEP will be reviewed and updated/revised at the end of each
phase (ref.to Milestones List) as per the outputs during the process and effects of the outputs on the further
activities. BEP versions related to phases will be listed.
PHASE or MILESTONE |
BEP VERSION |
DATE |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 1‑3: BEP versions as per project phases list
?
Executive summary will be written after finishing the BEP.
.....
I
Ref. to ISO-19650-2/5.4.1: confirm the names of the
individual(s) who will undertake the information management function within the
delivery team and ref. to ISO 19650-2/5.1.1, Include any agreed changes from
"Tender Response" Package. Ref. to ISO 19650-2/5.3.1, 5.3.2
Ú Documents:
4
OIR: Organizational Information Requirements
4
FRA_1: Functions Responsibilities & Authorities
(Individuals List)
4
REM-A_2: Information Management Assignment
Matrix-(Responsibility Matrix-Information Management Activities)
?
Project Information Management Functions, Task Information
Management Functions, Asset Information
Functions: (asset information
management should be involved in all stages of project delivery as defined in
Table 1, Refer to ISO 19650-1/7.2).
ACTOR
ROLES |
ACTOR |
|||||||
Functional |
Omniclass
|
Professional |
Omniclass
|
RESPONSIBLE
PARTY |
CONTACT
INFO |
|||
Abbr. |
Description |
Name |
e-mail |
phone |
||||
Company/ |
||||||||
e.g. Task Team |
|
e.g. Architect |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 2‑1: (FRA_2) Functions Responsibilities & Authorities (Individuals List)
I
Ref. to ISO-19650-2/Annex-A (Note: It is also called as
Responsibility Matrix-Information Management Activities or Information
management . responsibility matrix)
I Ref.to ISO-19650-1/3.1.1: responsibility matrix:
chart that describes the participation by various functions in completing tasks or deliverables [SOURCE:
ISO 37500:2014,
3.16 – modified]. Note
1 to entry: A responsibility matrix can indicate accountability, consultation and informing, alongside the obligation to complete tasks or deliverables.
I Ref.to ISO-19650-1/10.3: A responsibility matrix should be generated as part of the information delivery planning process in one or more levels of detail. The axes of a responsibility matrix
should identify:
·
information management functions; and
·
either project or asset information management tasks, or information deliverables as appropriate.
The content of a responsibility matrix should show the appropriate detail relevant to the axes.
Refer
to below document (under folder: Delivery_IMDocs/BEP):
Annex_2.1 = REM-A_3:
Information Management Assignment Matrix
I
Refer to Cl.4 for "Information Standard", and Cl. 5
for "Information Production Methods and Procedures"
Ú Documents:
4
EIR-APOP: Appointing Party's Exchange Information Requirements
4
REF_1: Project’s reference information and shared
resources
4
TEN-CR: Tender Response Requirements & Evaluation Criteria
4
MIS_1: Milestones List (Including detailed description of the
information at each key decision point)
4
INS_1: Project's Information Standard
4
PMP_1: Project's Information Production Methods and
Procedures
4
INP_1: Project's Information Protocol
4
OIR: Organizational Information Requirements
4
PIR: Project Information Requirements
4
AIR: Asset Information Requirements
4
ACR: Acceptance Criteria Manual
4
RAS_1: Risk Assessment Requirements
4
COL-PP: Collaboration Process & Procedures (within the CDE)
4
LOIN: Level of Information Need Manual
4
LOA: Level of Accuracy Table
4
CDE-SMP_1: Project's CDE Structure, Standards,
Methods, Procedures (Incl. Security Req.s and COL-PP)
4
LIB_1: Library Guide & Library Structure in Data
Environment
4
SHR_1: Shared Resources Guide & Shared Resources in Data
Environment
4
PoW_1: Plan of Work
4
INP_1: Project's Information Protocol
4
REF_1: Project’s reference information and shared resources
4
AAP: APOP Assurance Processes
4
QUA: Quality Assurance, Coordination & Issue Management
Manual
4
SUP: Supporting Information for LEAP
4
PSC: Project's
Schedule from Project Plan
I
Refer to Cl.3.2 for "Reference Information & Shared
Resources", Cl.6.1.2 for
"Acceptance Criteria", Cl.4 for "Information Standard", Cl.5
for "Information Production Methods and Procedures" .
....
I
Establish the appointing
party’s information requirements to be served during the appointment, and in
doing so shall consider their OIR, PIR and AIR. (ref. to. ISO 19650-2/5.2.1)
I
Include updates from PIR
content. Include handover requirements with referring to AIR.
I
PIR explain
the information needed
to answer or inform high-level strategic objectives within the
appointing party in relation to a particular built asset project. PIR are
identified from both the project management process and the asset management
process. A set of information requirements should be prepared for each of the
appointing party’s key decision points during the project. Repeat clients may
develop a generic set of PIR that can be adopted, with or without amendment, on
all of their projects. (Ref. to ISO-19650-1/5.4).
Refer to:
Ú Documents:
4 PIR: Project Information Requirements
Refer to: (under folder: Delivery_IMDocs)
?
Describe how BIM is used to achieve specific project goal at
different stages of the project.
? Following table is presented to describe how BIM is used to achieve specific
project goal at different stages of the project.
PRIORITY (high/med./low) |
GOAL (CoS) DESCRIPTION |
BIM USES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 3‑1: BIM Goals / BIM Objectives
?
The intended purpose for which the information will be used
by the appointing party.
....
? List of expected BIM use
cases and deliverables for each BIM use. Include value added use cases and
deliverable.
Ú Refer to: (below
documents are
under folder: Delivery_IMDocs/BEP)
Annex_7.1 = HLRM_1: Delivery team’s High Level Responsibility
Matrix
Annex_7.2 = DRM_0: Delivery Team’s Detailed Responsibility Matrix
Annex_3.3 = USE_2: BIM USE MATRIX
Annex_3.4 = BUA_2: BIM USE ANALYSIS
BIM USES ACROSS PHASES |
||||||||||||||||
BIM USE NO |
BIM USE NAME |
Appraisal |
Conceptual Design |
Schematic Design |
Design Development |
Technical Design |
Production Info.- |
Production Inf.-Rev. |
Tender Doc. |
Tender Action |
Mobilization |
Construction |
Handover/Close-out |
USE |
R&D-Model |
Demolition |
A |
B |
C |
D |
E |
F1 |
F2-6 |
G |
H |
J |
K1-5 |
K6-7 |
L |
M |
Z |
||
1A |
Existing Conditions Modeling |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1B |
Existing Conditions Modeling_ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1C |
Existing Conditions Modeling_ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2A |
5D Cost Estimation (Quantity takeoff &
Detailed Estimating) & Cost Man. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2B |
5D Budgetary Cost Model |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3 |
4D Planning, Scheduling & |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4 |
Site Analysis |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5 |
Programming |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6 |
Bespoke BIM object library authoring |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7 |
Design Reviews |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8 |
Code Validation_ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9 |
Code Validation_ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10 |
Engineering Analysis_Sustainability Evaluation
(Leed Evaluation/ Leed Credit Documentation) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11 |
Engineering Analysis_Lighting Analysis (Daylight
integration) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12 |
Engineering Analysis_Energy Analysis (Energy
Modeling, Sun Studies, Daylight Analysis) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13 |
Engineering Analysis_Structural An. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14 |
Engineering Analysis_Mechanical A. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15 |
Engineering Analysis_Geotechnical |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16 |
Environmental (Passive) Analysis |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17 |
Fire Safety-Active (Code Validation /Analysis and
Report with Proposals, Constultancy) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
18 |
Fire Safety-Passive (Code Validation/Analysis and
Report with Proposals, Constultancy) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
19 |
Acoustical Analysis & |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
20 |
Design Authoring_Architectural |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
21 |
Design Authoring_Structural / |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
22 |
Design Authoring_Mechanical |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
23 |
Design Authoring_ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
24 |
Design Authoring_Plumbing |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
25 |
Design Authoring_Electrical |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
26 |
Design Authoring_Civil Engineering |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
27 |
Design Authoring_Landscape |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
28 |
Elevator (& Escalator) Planning & Des. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
29 |
Zone Analysis and Zonning |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
30a |
Facade Design (& Engineering)- |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
30b |
Facade Design (& Engineering)- |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
30a |
Facade Design (& Engineering)- |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
30b |
Facade Design (& Engineering)- |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
30a |
Facade Design (& Engineering) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
31 |
Value Engineering Value Management&Design
Optimization (&Tenant/Operator Build Out) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
32 |
COBie Data Set/COBie Deliverables |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
33 |
Construction Drawing Production |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
34 |
3D Coordination/Clash Avoidance, |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
35 |
3D Control and Planning |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
36 |
Shop Model and Drawing |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
37 |
Digital Fabrication |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
38 |
Mechanical/ Equipment Maintenance Clearance,Space
Mod. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
39 |
Site Utilization Planning/ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
40 |
As-Built Model |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
41 |
Commissioning |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
42 |
Record Modeling |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
43 |
Agency-Marketing/Disposal to Market |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
44 |
Pedestrian simulation (hazard & dwell) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
45 |
Emergency Management (Security assessment&
disaster planning) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
46 |
Space Planning/Management |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
47 |
Asset Management |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
48 |
Building System Analysis (Operational) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
49 |
Building (Preventative) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
50 |
Model for Maintenance Training |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
51 |
Building System Automation |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 3‑2: BIM USES ACROSS
PROJECT PHASES
?
The Intended Procurement Route will be mentioned as schema
(or table) with a short description of the organization.
.....
Table 3‑3: PRS _2: Procurement Route (Schema & Table)
?
How to use PLQ_1 will be mentioned. For each task team's
self-assessment or for future possible assessment of actors such as
sub-contractors PLQ_1 will be used.
?
Project specific most important Plain/Pre-Qualification
Questions will be highlighted with referring to Annex_3.5.
.....
Ú Refer to: (under folder:
Delivery_IMDocs)
Appendix_3.5 = PLQ_1 : Plain/Pre-Qualification Questions
? Ref. to ISO-19650-2/5.2.1.b. Ref. to ISO-19650-1/3.3.16 (Level of
Information Need: Framework
which defines the extent and granularity of information. Note 1 to entry:
One purpose
of defining the level
of
information need is to prevent
delivery of too much information.)
Ref.
to ISO-19650-1/11.2:
·
The level of information deliverable should be determined according
to its purpose. This should include the appropriate determination of quality,
quantity and granularity of information. This is referred to as its level of
information need and this can vary from deliverable to deliverable.
·
A range of metrics exist to determine levels of information need. For example, two complementary but
independent metrics can define the geometrical and alphanumerical content in terms of quality, quantity and granularity. Once these metrics have been
defined, they should be used to determine the
levels of information need across the whole project or asset. All this should be described
clearly within the OIR, PIR,
AIR or EIR.
·
The levels of information need should be determined by the minimum
amount of information needed to answer each
relevant requirement and no more. Anything beyond this minimum is considered as waste. Lead appointed parties should consider the risk that importing
object information automatically into
information models might introduce a higher level of information need than is required.
·
The relevance of an information deliverable is not always correlated to its granularity. Level of
information need is, however, closely linked to the federation strategy
·
The granularity of alphanumerical information
should be considered to be at least as important as that of geometrical
information.
? Mention main objectives of "Level of Information Need"
to be used in the project with referring to LOIN_2
....
Ú
Refer to:
Annex_7.1 = HLRM_1: Delivery team’s High Level Responsibility
Matrix
Annex_7.2 = DRM: Delivery Team’s Detailed Responsibility Matrix
(Initial/Template)
Refer to (under folder: Delivery_IMDocs/BEP) below doc. for the desc. of each "Level of Information Need" in detailed.
Annex_3.6 = LOIN_2: Level of Information Need Manual
I Existing metrics: LOMD (Level of
Model Definition) = LOD(Level of Model Detail)+LOI(Level of Model Information)
/ LOD (Level of Development):
I Table 3.4 below will be updated as per
CEN/TC 442-prEN17412 Level of Information Need
Standard (when it is available)
|
LOMD |
LOD |
DEFINITION |
||
LOD |
LOI |
LOG |
LOI |
||
LOMD1/LOD100 |
|
|
|
|
Pre-Design Phase
(Symbolic-Brief) |
LOMD2/LOD100 |
|
|
|
|
Conceptual |
LOMD3/LOD200 |
|
|
|
|
Schematic Design Phase
(Generic-Definition) |
LOMD4/LOD300 |
|
|
|
|
Design Development |
LOMD5/LOD350 |
|
|
|
|
Construction Documents by
Disciplines for Bidding |
LOMD6/LOD400 |
|
|
|
|
Shop Drawing (During
construction-Build&Commission) |
LOMD2/LOD500 |
|
|
|
|
As Built & Operations
(As Built) |
|
|
|
|
|
|
|
|
|
|
|
|
Table 3‑4: Level of Information Need Classification Table (as per BIM Uses)
?
Ref.
to ISO-19650-2/5.2.1.d "The supporting
information that the prospective lead appointed party might need, to fully
understand or evaluate each information requirement or its acceptance criteria.
When establishing this existing asset information, shared
resources, supporting documents or guidance material, references to relevant
international, national or industry standards, and exemplars of similar information
deliverables will be taken into consideration.
.....
NO |
FILE NAME |
DESCRIPTION |
FOLDER IN CDE |
1 |
|
|
|
2 |
|
|
|
3 |
|
|
|
4 |
|
|
|
5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 3‑5: Supporting
Information List (incl. Location)
Ú Refer to: ISO-19650-2/5.2.1.e, PSC: Project's Schedule
from Project Plan
?
In the below table following information was mentioned for
your kind consideration;
·
dates that each requirement has to be met with regarding the time needed by the appointing party to
review and accept information and the appointing party’s internal assurance
processes (ref. to. ISO 19650-2/5.2.1.e)
·
detailed description of the information at each of the key
decision point (Ref .to
ISO-19650-2/5.1.2, 5.1.3, 5.2.1)
I
For detailed Plan of Work please review and apply to; (under folder:
Delivery_IMDocs)
Appendix_3.7 = PoW-1: Plan of Work (with Milestones & Dates)
MILESTONES (& DETAILED PHASES) & KEY
DECISION POINTS SCHEDULE |
|||||||||
MAIN PH. |
CODE |
DEFINITION |
KEY DECISION POINT |
START |
FINISH |
STATUS |
|||
CODE |
DEFINITION |
||||||||
PREPARATION |
INCEPTION |
A |
Appraisal / Strategic Definition |
- |
- |
../Jan/.. |
../m/.. |
Start |
|
CONCEPTUAL DESIGN |
B |
1 |
Proceed to Conceptual Design |
KDP-1 |
Decision & Comments for to proceed on
Conceptual Des. |
../m/.. |
../m/.. |
.. |
|
B |
2 |
Design Brief/Conceptual Design |
- |
- |
../m/.. |
../m/.. |
.. |
||
B |
3 |
*Data
Drop 1 |
../m/.. |
../m/.. |
.. |
||||
B |
4 |
Approval:
Design Notice to Proceed |
KDP-2 |
Apop's Approval and comments for to start
Schematic Design ("Basic Project” contract agreement) |
../m/.. |
../m/.. |
.. |
||
B |
5 |
- |
KDP-3 |
Basic MEP Design Criterias Decision |
../m/.. |
../m/.. |
.. |
||
B |
6 |
*Data
Drop 1 Package Update |
../m/.. |
../m/.. |
.. |
||||
DESIGN |
SCHEMATIC DESIGN |
C |
1 |
Schematic Design |
- |
- |
../m/.. |
../m/.. |
.. |
C |
2 |
*Data
Drop 2 |
../m/.. |
../m/.. |
.. |
||||
C |
3 |
Approval
(Appointing Party): |
KDP-4 |
Apop's Approval & Comments for to start
Design Development |
../m/.. |
../m/.. |
.. |
||
C |
4 |
Local
Public Authority: Interview with local authorities |
- |
- |
../m/.. |
../m/.. |
.. |
||
C |
5 |
Update of MEP Design Criterias & Apop's
Comments as per the interviews with Local Authorities |
KDP-5 |
Updated MEP Design Criteria & Comments |
../m/.. |
../m/.. |
.. |
||
C |
6 |
*Data
Drop 2 Package Update according to C5 |
../m/.. |
../m/.. |
.. |
||||
C |
7 |
Approval
(Local Public Authority): Design Notice to Proceed |
KDP-6 |
Approval from Local Public Authorities for to
start Design Development Process |
../m/.. |
../m/.. |
.. |
||
DESIGN DEVELOPMENT |
D |
1 |
Design Development Start |
- |
- |
../m/.. |
../m/.. |
.. |
|
D |
1a |
Design Development Check Point - %25 completion |
- |
- |
../m/.. |
../m/.. |
.. |
||
D |
1b |
Design Development Check Point -%50 completion |
- |
- |
../m/.. |
../m/.. |
.. |
||
D |
1c |
Design Development Check Point - %75 completion |
- |
- |
../m/.. |
../m/.. |
.. |
||
D |
1d |
Design development completion |
- |
- |
../m/.. |
../m/.. |
.. |
||
D |
2 |
*Data
Drop 3 |
- |
- |
../m/.. |
../m/.. |
.. |
||
D |
3 |
Approval
(Appointing Party): |
KDP-7 |
Apop's Approval & Comments for to start
Technical Design Process |
../m/.. |
../m/.. |
.. |
||
D |
4 |
Approval
(&Comments): from Local Building Authority/Application for detailed planning
permission |
KDP-8 |
Comments from Local Building Authority |
../m/.. |
../m/.. |
.. |
||
D |
5 |
*Data
Drop 3 Package Update according to D3&D4 |
../m/.. |
../m/.. |
.. |
||||
TECHNICAL DESIGN |
E |
1 |
Technical Design-Start |
- |
- |
../m/.. |
../m/.. |
.. |
|
E |
1a |
Technical Design- Check Point %25 completion
|
- |
- |
../m/.. |
../m/.. |
.. |
||
E |
1b |
Technical Design- Check Point %50 completion
|
- |
- |
../m/.. |
../m/.. |
.. |
||
E |
1c |
Technical Design- Check Point %75 completion |
- |
- |
../m/.. |
../m/.. |
.. |
||
E |
1c |
Technical Design- Completion |
- |
- |
../m/.. |
../m/.. |
.. |
||
E |
2 |
*Data
Drop 4 |
../m/.. |
../m/.. |
.. |
||||
E |
3 |
Approval
(Appointing Party): |
KDP-9 |
Apop's Approval & Comments for to start
Construction Documents Process |
../m/.. |
../m/.. |
.. |
||
E |
4 |
Local
Public Authority: Interview with local authorities |
- |
- |
../m/.. |
../m/.. |
.. |
||
E |
5 |
*Data
Drop 4 Package Update according to E3 & E4 |
../m/.. |
../m/.. |
.. |
||||
PRE-CONSTRUCTION |
CONSTRUCTION / IMPLEMENTATION DOCUMENTS |
F |
1 |
Production Information- |
- |
- |
../m/.. |
../m/.. |
.. |
F |
1a |
Construction Documents Check Point -01 |
- |
- |
../m/.. |
../m/.. |
.. |
||
F |
1b |
Construction Documents Check Point -02 |
- |
- |
../m/.. |
../m/.. |
.. |
||
F |
1n |
Construction Documents Check Point -n |
- |
- |
../m/.. |
../m/.. |
.. |
||
F |
2a |
Production Information: Construction Documents
End & Getting the OCTis Report |
- |
- |
../m/.. |
../m/.. |
.. |
||
F |
2b |
*Data
Drop 5 |
CONSTRUCTION DOCUMENTS |
../m/.. |
../m/.. |
.. |
|||
F |
3a |
Approval
(Appointing Party): |
KDP-10 |
Apop's Approval & Comments for to start
application for statutory approvals |
../m/.. |
../m/.. |
.. |
||
F |
3b |
Update as per Apop's Comments |
- |
- |
../m/.. |
../m/.. |
.. |
||
F |
4 |
Approval
(Local Building Authority) Application for statutory approvals & the Building License |
KDP-11 |
Statutory approvals & Receiving the Building
License |
../m/.. |
../m/.. |
.. |
||
F |
5 |
*Data
Drop 5 Package Update |
CONSTRUCTION DOCUMENTS-UPDATE |
../m/.. |
../m/.. |
.. |
|||
TENDER DOCUMENTATION |
F |
6a |
Production Information- Final Review by all
parties and final comments for tender documentation process |
- |
- |
../m/.. |
../m/.. |
.. |
|
F |
6b |
Approval (Appointing Party): |
KDP-12 |
Approval for proceed on tender documentation
& Site Safety |
../m/.. |
../m/.. |
.. |
||
F |
6c |
Site Safety Project Approval |
KDP-13 |
Aproval by Apop & Local Public Authority |
../m/.. |
../m/.. |
.. |
||
G |
Tender Documentation |
- |
- |
../m/.. |
../m/.. |
.. |
|||
H |
1 |
Tender Action |
- |
- |
../m/.. |
../m/.. |
.. |
||
H |
2 |
Tender Action- Approval |
KDP-14 |
Apop's Approval&Comments |
../m/.. |
../m/.. |
.. |
||
H |
3 |
*Data
Drop 6 (Updated as per F6a-H3) |
TENDER DOCUMENTS PACKAGE |
../m/.. |
../m/.. |
.. |
|||
CONSTRUCTION |
MOBILIZATION |
J |
1 |
Construction Bid Received |
KDP-15 |
Bid approval by Apop/Client |
../m/.. |
../m/.. |
.. |
J |
2 |
Approval
Local Public Authority: Construction Notice to Proceed |
KDP-16 |
Approval of the “Construction Area” (requested by
the Construction Com./GC) by Local Public Authority |
../m/.. |
../m/.. |
.. |
||
J |
3a |
Mobilization |
- |
- |
../m/.. |
../m/.. |
.. |
||
J |
3b |
Apop/Leap Decision |
KDP-17 |
Decision for shop drawing responsibilities and construction
administration |
../m/.. |
../m/.. |
.. |
||
SHOP DRAWINGS AND CONSTRUCTION |
K |
1 |
Shop Drawing Phase -Start (In line with
executions-In each check point necessary approvals from Apop will be taken
for further executions) |
- |
Approval (by Apop) of |
../m/.. |
../m/.. |
.. |
|
K |
2 |
Construction
Start-Excavation |
KDP-18 |
Approval (by Apop) of |
../m/.. |
../m/.. |
.. |
||
K |
3 |
Construction
Works |
KDP-19 |
Approval (by Apop) of |
../m/.. |
../m/.. |
.. |
||
K |
3a |
Construction Works Check Point-A1 (to be
determined special for the project) |
KDP-20a |
Approval (by Apop) of |
../m/.. |
../m/.. |
.. |
||
K |
3b |
Construction Works Check Point-A2 (to be
determined special for the project) |
KDP-20b |
Approval (by Apop) of |
../m/.. |
../m/.. |
.. |
||
K |
3n |
Construction Works Check Point-An (to be
determined special for the project) |
KDP-20n |
Approval (by Apop) of |
../m/.. |
../m/.. |
.. |
||
K |
4a |
Substantial
Completion- |
KDP-21 |
Completion of the approvals (by Apop) of all Shop Drawing Package |
../m/.. |
../m/.. |
.. |
||
K |
4b |
*Data
Drop 7 |
SHOP DRAWING PACKAGE |
|
|
|
|||
K |
4c |
Construction Works Check Point -B2 (to be
determined special for the project) |
- |
- |
../m/.. |
../m/.. |
.. |
||
K |
4n |
Construction Works Check Point -Bn (to be
determined special for the project) |
- |
- |
../m/.. |
../m/.. |
.. |
||
K |
5 |
Construction
Completion |
- |
- |
../m/.. |
../m/.. |
.. |
||
HANDOVER/CLOSE OUT |
K |
6 |
Handover / Close-out: |
KDP-25 |
Inspection & Comments by Apop |
../m/.. |
../m/.. |
.. |
|
K |
7a |
Handover / Close-out: Construction Work Revisions
as per comments |
- |
- |
../m/.. |
../m/.. |
.. |
||
K |
7b |
*Data
Drop 8 |
AS BUILT |
../m/.. |
../m/.. |
.. |
|||
K |
7c |
Approval
(Appointing Party): |
KDP-26 |
Apop's Approval & Comments for to start
application for statutory approvals |
../m/.. |
../m/.. |
.. |
||
K |
7d |
*Data
Drop 8 Package Update |
AS BUILT-UPDATE |
../m/.. |
../m/.. |
.. |
|||
K |
7e |
Approval
(Appointing Party & All Parties): Notice to Acceptance |
KDP-27 |
Acceptance Certificate (construction |
../m/.. |
../m/.. |
.. |
||
OPERATIONS |
USE (POST PRACTICAL COMPLETION) |
L |
1 |
OPERATION/USE-Post Practical Completion:
Administration of the building contract after Practical Completion and making
final inspections. |
- |
- |
../m/.. |
../m/.. |
.. |
L |
2 |
*Data
Drop 9 OPERATION/USE: |
PIM to
AIM |
../m/.. |
../m/.. |
.. |
|||
L |
3 |
OPERATION/USE:Apop's/Operator's Approval |
KDP-28 |
Apop/Operator Notice to Proceed Facility
Management |
../m/.. |
../m/.. |
.. |
||
L |
4 |
OPERATION/USE-Post Practical Completion:
Assisting building user during initial occupation period. |
- |
- |
../m/.. |
../m/.. |
.. |
||
MAINTENANCE&DEVELOPMENT |
M |
1a |
R&D-Model Maintenance & Development |
- |
- |
../m/.. |
../m/.. |
.. |
|
M |
1b |
*Data
Drop 10 |
AIM TO
PIM |
../m/.. |
../m/.. |
.. |
|||
M |
2a |
Renovation Decision-1 |
KDP-29 |
Renovation Decision-1 |
../m/.. |
../m/.. |
.. |
||
M |
2b |
*Data
Drop 11 |
AIM TO
PIM |
../m/.. |
../m/.. |
.. |
|||
M |
2n |
Renovation Decision-n |
KDP-N |
Renovation Decision-n |
../m/.. |
../m/.. |
.. |
||
M |
2n |
*Data
Drop n |
AIM TO
PIM |
../m/.. |
../m/.. |
.. |
|||
Closure |
Z |
Closure/Demolition |
- |
- |
../m/.. |
../m/.. |
.. |
Table 3‑6: Milestones Schedule (MIS_1, Including Explanations of Key Decision Point Decisions and Dates to be met)
I
Please refer to
"PIT_1" for "Project Information" & Ref. to. ISO
19650-2/5.1.6, 5.2.2)
Ú Documents:
4
LIB_1: Library Guide & Library Structure in Data
Environment
4
SHR_1:Shared Resources Guide & Shared Resources in Data
Environment
.....
? Mention how to use the library, library structure, how to create new objects and how to use the existing ones, exception rules, library procedures..
.....
Figure 3‑1: Library Structure
? Mention how to use shared resources, shared resources folder structure, who will do what to have a proper shared resource and which shared resource is appropriate to use and current, the procedures.
.....
SHARED
RESOURCES FOLDER |
||
XXXXXX/06-RESOURCE/SHARED_RESOURCES FOLDER CONSISTS OF THREE SUB-FOLDERS MENTIONED BELOW |
||
ARCHIVE Old resources files will be archived in
separate sub-folders folders as per dates. Sub-folder:YYYY/MM/DD |
SHARED (Responsible party will share the file
first here. If the file needs review by all parties (such as new survey). |
PUBLISHED (Development plan Legal Documents of Site. etc) |
Table 3‑7: Shared
Resources Folder
? With referring to LIB and SHR mention all the procedures related to REF.
.....
NO |
FILE NAME |
DESCRIPTION |
REVISION (METADATA) |
FOLDER IN CDE |
1 |
|
|
|
|
2 |
|
|
|
|
3 |
|
|
|
|
4 |
|
|
|
|
|
|
|
|
|
Table 3‑8: REF_1: Project’s reference information and shared resources
I Ref.to ISO-19650-2/5.1.8: The appointing party shall establish the project’s information protocol,
as defined below, including any
associated license agreements, which will, subsequently and
appropriately, be incorporated into all appointments. In doing this,
the appointing party shall consider:
specific obligations of the appointing party, prospective lead appointed
parties and prospective appointed parties relating to the management or
production of information, including the use of the project’s common data
environment;
·
any warranties or liabilities associated to
the project information model; background and foreground intellectual property
rights of information; the use of existing asset information; the use of shared
resources; the use of information during the project, including any associated
licensing terms; and the re-use of information following the appointment or in
the event of termination.
Ú Refer to: (under folder:
Delivery_IMDocs)
Appendix_3.8 = INP_2: Project’s Information Protocol
? Mention most important, crucial protocol items which every single user should be aware of.
? Mention the items which are changing during BEP's evolution throughout the phases, milestones.
.....
I
Ref. to
ISO-19650-2/5.1.7: The appointing party shall establish (implement, configure
and support) the project’s common data environment (CDE) to serve the overall
requirements of the project and to support the collaborative production of
information. The project’s
common data environment shall enable:
a) each information container to have a
unique ID, based upon an agreed and documented convention comprised of a number
of fields separated by a delimiter;
b) each field to be assigned a value from an
agreed and documented codification standard;
c) each container to have the following
attributes assigned:
·
status
(suitability); revision (and version); classification (in accordance with the
framework defined in ISO 12006-2)
d)
the ability for information containers to transition between states;
e)
the recording of the name of user and date when information container revisions
transition between each
state;
and
f)
controlled access at an information container level.
It
is strongly recommended that the project CDE is in place prior to issuing the
invitation to tender, so that information can be shared with tendering
organizations in a secure manner.
The
appointing party can also appoint a third-party to host, manage or support the
project’s CDE. In this case, it is recommended that this is done as a separate
appointment before procurement of any other appointed party starts. Or the
appointing party can also, at a later date, appoint an appointed party to take
over the hosting, management or support of the project CDE. In either case, it
is recommended that the appointing party defines a functional and
non-functional requirements specification.
? The structure of CDE created according to the ISO-19650 and standards mentioned in 3.3.1 and 4.4.2
.....
Figure 3‑2: CDE concept in ISO 19650-1
? Mention all standards, methods and procedures of CDE which will be used during the Life Cycle.
.....
Figure 3‑3: Revision control during Work in Progress (WIP)
Figure 3‑4: Revision control of Shared information
Figure 3‑5: Revision control of Published information containers
STEP |
DESCRIPTION |
STATE |
REVISION |
STATUS |
0 |
||||
1 |
||||
2 |
||||
3 |
||||
4 |
||||
5 |
||||
6 |
||||
.. |
Table 3‑9: EXAMPLE OF AN INFORMATION CONTAINER DEVELOPMENT IN CDE (AS A GUIDE)
Figure 3‑6: Figure of the schema illustrating the development
process mentioned in Table 3.9
Figure 3‑7: Project's
Folder Structure in Cloud
Figure 3‑8: Project's
Folder Structure in local servers of the actor
I Ref. to ISO-19650-2/5.3.3, 5.3.5
? Explain the training requirements with referring to below table and mention the update conditions of the training plan.
.....
TRAINING
SUBJECT |
RELATED
BIM USE (CODE) |
TEAM
TO BE TRAINED |
INDIVIDUALS
IN THE TEAM TO BE TRAINED (as
number) |
START DATE (dd/Mon/yy) |
FINISH DATE (dd/Mon/yy) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 3‑10: Plan of Training
I Ref.to ISO-19650-2/5.4.1: agree with the appointing party any additions
or amendments to the project information standard).
I Ref.to ISO-19650-2/5.2.1, 5.2.4,
I Ref.to ISO-19650-2/5.3.2: f) In Pre-App. BEP include, any proposed additions or
amendments to the project’s information standard that the delivery team require
to facilitate the effective:
·
exchange of information between task teams,
·
distribution of information to external parties, or
·
delivery of information to the appointing party;
I Ref.to ISO-19650-2/5.1.4: The appointing party shall establish any
specific information standards required by the appointing party’s organization
within the project’s information standard. In doing this, the appointing party
shall consider:
a) the exchange of information:
·
within the
appointing party’s organization,
·
between the
appointing party and external stakeholders,
·
between the
appointing party and external operators or maintainers,
·
between the
prospective lead appointed party and the appointing party
·
between prospective appointed parties on the same project, and
·
between interdependent projects;
b) the means of structuring and
classifying information;
c) the method of assignment for level of
information need; and
d) the use of information during the
operational phase of the asset.
I This section includes updates from "Invitation to
Tender" and "Tender Response Packages"
Ú Documents:
4
REM-A_3: Information Management Assignment Matrix
4
FRA_2: Functions Responsibilities & Authorities
(Individuals List )
4
PRS_2: Procurement Route (Schema & Table)
4
COL-PP: Collaboration Process & Procedures (within the
CDE)
4
CDE_2: Project's CDE Structure, Standards, Methods, Procedures
4
(Incl. Security Requirements and COL-PP)
4
ICN_0: Information Container Naming Requirements
4
CLM: Project's Classification System & Metadata
I
Construction tolerances for all disciplines are mentioned in
Cl. 3.1.3
.....
I Ref. to ISO-19650-1/3.3.12, ISO-19650-1/12.1, ISO 13567‑2
I Explain each type of information container naming requirement which will be used in the project.
I Mention each type of designator which will be used in the project. (Below examples were given.)
I Mention the method of naming rooms / areas, stairs, windows, doors and other element (Such as room naming will start from the staircase as clockwise etc.).
The revision and status are required to track the progression of a file or document to its completion and authorization. The revision and status code need to be part of the attributed metadata, not part of the file name. For "Metadata" please refer to Clause 4.2.2 below.
.....
PROJECT |
|
ORIGINATOR |
|
VOLUME/ |
|
SUB- |
|
LEVELS & |
|
TYPE/ |
|
FUNCTION |
|
NUMBER |
|
DOCUMENT
|
NUMBER |
||||||||||||||
111803 |
- |
XXX |
- |
XXXX |
- |
XXXX |
- |
XX |
- |
XXX |
- |
XX |
- |
XX |
XXXX |
Table 4‑1: FILE, & SHEET CODE /FILE (FOR PUBLICATION OF THE SHEET) NAME
.....
DESIGNATOR / NUMBER |
|
PROJECT'S FULL NAME |
M3BEPG11-Olympic_Tower |
PROJECT'S CODE |
M3BEPG11-OT |
PROJECT'S NUMBER |
111803 |
Table 4‑2: Project Designators
.....
Phase
Code |
DEFINITION |
||
Classification (e.g.Omniclass
|
Code |
||
10 |
A |
Appraisal / Strategic Definition |
|
20 |
B |
Design Brief/Conceptual Design |
|
30 |
C |
Schematic Design |
|
40 |
D |
Design Development |
|
40 |
E |
Technical Design |
|
50 |
F |
Production Information (Construction Documents, Review &
Site-Safety Approval |
|
50 |
G |
Tender Documentation |
|
50 |
H |
Tender Action |
|
60 |
J |
Mobilization |
|
60 |
K |
Construction & Shop Drawings |
|
70 |
K |
Handover / Close-out |
|
80 |
L |
USE-Post Practical Completion |
|
80 |
M |
R&D-Model Maintenance & Development |
|
90 |
Z |
Demolition |
|
Table 4‑3: Originator (Design Phases) Designators
.....
ZONE |
SUB-ZONE |
|
ZONE |
SUB-ZONE |
|
ZONE |
SUB-ZONE |
|
ZONE |
SUB-ZONE |
Table 4‑4: Zone & Sub-Zone Designators
.....
LEVEL |
DESCRIPTION |
|
LEVEL |
DESCRIPTION |
|
LEVEL |
DESCRIPTION |
|
LEVEL |
DESCRIPTION |
RF |
ROOF |
... |
..... |
... |
..... |
... |
..... |
|||
... |
..... |
... |
..... |
... |
..... |
B2 |
Basement
-2 |
|||
... |
..... |
... |
..... |
01 |
1st
Floor |
B3 |
Basement
-3 |
|||
... |
..... |
... |
..... |
GF |
Ground
Fl. |
B4 |
Basement
-4 |
|||
... |
..... |
... |
..... |
B1 |
Basement
-1 |
FN |
Foundation |
Table 4‑5: Level Designators
.....
MAIN SHARED
RESOURCES |
|
MODELS
/DRAWINGS |
|||
EIR |
Exchange Information Requirements |
M2D |
2d Model File |
||
OIR |
Organizational Information Requirements |
M3D |
3d Model File |
||
COR |
Coordination Model (Naviswork, Solibri) Clash Rendition |
||||
AIR |
Asset Information Requirements |
ANM |
Animation (of the Model) |
||
PIR |
Project Information Requirements |
VSM |
Visualization File (of the Model)/ Model Rendition |
||
INP |
Project Information Protocol |
VIS |
Visualization File (Render) |
||
BEP |
BIM Execution Plan |
COM |
Federated/Combined Model |
||
SUR |
Surveys |
DRW |
2D Drawing |
||
MODELS
/DRAWINGS |
|||||
BOQ |
Bill of
quantities |
|
SCH |
Schedule |
|
CMT |
Comments |
SNL |
Snagging List |
||
COP |
Correspondence |
SPC |
Specification |
||
CSP |
Cost Plan |
STC |
Structural
Calculations |
||
DBS |
Database |
TQS |
Technical Survey |
||
FNT |
File Note |
WCD |
Work change
directives |
||
HSF |
Health and
Safety |
ASI |
Architectural supplemental instruction |
||
MIA |
Minutes /Action
Notes |
COR |
Change order
request |
||
MOS |
Method of
Statement |
CCD |
Construction change directive |
||
PPT |
Presentation |
COP |
Change order proposal |
||
PRG |
Programme |
DCVR |
Design clarification verification request |
||
RDT |
Room Data Sheet |
FDR |
Field deficiency
report |
||
RFI |
Request for
Information |
NCR |
Nonconformance report |
||
RPT |
Report |
CVN |
Contract
violation notice |
||
SCA |
Schedule of
accommodation |
ORS |
Observation reports |
||
Table 4‑6: File Type Designators
.....
DISCIPLINE DESIGNATORS
(EXCLUDING MEP) |
||||
DESIGNATOR |
AS NUMBER |
DESCRIPTION |
||
LEVEL 1 |
LEVEL 2 |
LEVEL 1 |
LEVEL 2 |
|
SYSTEM |
SUB-SYSTEM |
SYSTEM |
SUB-SYSTEM |
|
Z |
0 |
00 |
00 |
General (non-specific) |
A |
0 |
01 |
00 |
Architectural-All |
A |
F |
01 |
00 |
Architectural-Facade Engineer |
S |
0 |
02 |
00 |
Structural-All |
S |
S |
02 |
01 |
Strtuctural-Steel Structure |
I |
0 |
03 |
00 |
Interior Design (ers) |
L |
0 |
06 |
00 |
Landscape Architects |
C |
I |
11 |
00 |
Civil-Infrasructure_Drainage/Waste Water Management |
B |
0 |
10 |
00 |
Building Surveyors |
G |
L |
12 |
00 |
GIS, land surveyors |
Q |
S |
13 |
00 |
Quantitiy Surveyors |
K |
0 |
20 |
00 |
Client |
W |
0 |
21 |
00 |
Contractor/Design Builder |
X |
0 |
22 |
00 |
Sub-contractor |
Y |
A |
23 |
00 |
Acoustical Consultant /Analysis |
Y |
F |
23 |
00 |
Fire Consultant/Engineer (Active and Passive) |
Y |
L |
23 |
00 |
Lighting Consultant/Engineer |
Y |
E |
23 |
00 |
Elevators & Escalators Sub-Contractor/Consultant |
O |
F |
24 |
00 |
Operations-Facilities
Manager |
Table 4‑7: Discipline Designators (Excluding MEP)
DISCIPLINE DESIGNATORS (MEP) |
||||
DESIGNATOR |
AS NUMBER |
DESCRIPTION |
||
LEVEL 1 |
LEVEL 2 |
LEVEL 1 |
LEVEL 2 |
|
SYSTEM |
SUB-SYSTEM |
SYSTEM |
SUB-SYSTEM |
|
M |
- |
04 |
00 |
MEP related general reports etc. |
M |
0 |
04 |
01 |
Mechanical-General (Calculations & Pre-Design All Mechanical) |
M |
E |
04 |
02 |
Mechanical-Combined Services |
M |
A |
04 |
03 |
Mechanical-HVAC_Air Conditioning |
M |
F |
04 |
04 |
Mechanical-Fire Protection (Fire&Safety, Smoke Control) |
M |
H |
04 |
05 |
Mechanical-HVAC_Heating |
M |
W |
04 |
06 |
Mechanical-HVAC_Chilled Water & Refrigeration |
M |
V |
04 |
07 |
Mechanical-HVAC_Ventilation |
P |
0 |
04 |
08 |
Plumbing-General (Calculations & Pre-Design All Plumbing) |
P |
P |
04 |
09 |
Plumbing-Water Supply_Domestic/Potable Water System |
P |
H |
04 |
10 |
Plumbing-Water Supply_Hot Water |
P |
D |
04 |
11 |
Plumbing-Drainage (Sanitary Sewer Systems) |
P |
F |
04 |
12 |
Plumbing-Fixtures |
P |
S |
04 |
13 |
Plumbing-Storm/Rain Water |
E |
0 |
05 |
01 |
Electrical-General |
E |
A |
05 |
02 |
Electrical-Public Adress |
E |
C |
05 |
03 |
Electrical-Cable Routing/Cable Containment |
E |
D |
05 |
04 |
Electrical-Low Current (IT & Communication, CCTV) |
E |
F |
05 |
05 |
Electrical-Fire Detection (Fire Alarm) Systems |
E |
G |
05 |
06 |
Electrical-Grounding/Earthing (Internal&External) |
E |
L |
05 |
07 |
Electrical-Lighting |
E |
M |
05 |
08 |
Electrical-Mechanical Systems' Electrical Services |
E |
P |
05 |
09 |
Electrical-Lightning Protection |
E |
S |
05 |
10 |
Electrical-Security & Access Control Systems |
E |
T |
05 |
11 |
Electrical-Telecommunication |
E |
V |
05 |
12 |
Electrical-Billing&Building Management |
E |
W |
05 |
13 |
Electrical-Power Systems |
Table
4‑8: Discipline Designators (MEP)
.....
DISCIPLINE |
ZONE |
SUB- |
FLOOR/ BUILDING PART NAME |
TYPE |
|||||
LEVEL 1 |
LEVEL 2 |
||||||||
XX |
XX |
- |
XXXX |
- |
XXXX |
- |
(e.g: Parking-1) |
- |
(e.g: Floor Plan) |
Table
4‑9: Sheet/View Naming
ZONE |
|
SUB-ZONE |
|
WORKSET DESCRIPTION (underscore in between) |
|
XXXX |
- |
XXXX |
- |
(e.g: Interior_Wall) |
Table 4‑10: Workset Naming
.....
NUMBER
DESIGNATOR OF SHEETS & PUBLICATION FILES (PDF etc.) |
|
Sample=
...-A0-050011: 050011: 11th sheet of Architectural Details |
|
DOCUMENT
GROUP TYPE DESIGNATOR (MAIN DESIGNATOR) |
|
00-09 will be used for all group types. Group Type Designator will be
infront of these. |
|
00 |
General:Symbol legend, abbreviation, general notes |
01 |
Plans |
02 |
Elevations |
03 |
Sections |
04 |
Large Scale Drawings |
05 |
Details |
06 |
Schedules and Diagrams |
07 |
Reflected Ceiling Plans (RCP) |
08 |
Flooring (Floor Pattern) |
09 |
3D drawings |
10-11 will be used for the type of submissions which are out of 0 to 9
content. |
|
10 |
Special for Strtuctural Discipline |
11 |
Special for MEP-HVAC&Gas |
12 |
Special for MEP-Plumbing |
13 |
Special for MEP-Fire |
14 |
Special for Electrical |
15 |
Special for Other Disciplines |
16 |
Non drawing documents (Reports, Moms etc.) |
17 |
Submissions as file (Revit Model, IFC etc.) |
Table
4‑11: Number Designator
I
ISO 19650‑1 states that
classification should be to a system in accordance with ISO 12006‑2.
.....
I
Ref.
to ISO-19650-1/3.3.13
I
Ref.
to ISO-19650-1/12.1: Each information container managed through the CDE
should have metadata including:
·
a revision code, in accordance with an agreed standard
for example IEC 82045-1; and
·
a status code, showing the permitted
use(s) of information.
.....
Table 4‑12:Project's Classification System
? Explain the metadata standards to be complied with. Below some sample information is mentioned.
.....
P |
01 |
. |
01 |
|
Letter for Prefix=P or C |
Two numeric integer values |
Two numeric integer values following a decimal point representing the WIP (Work in Progress) version of the primary revision. |
||
Table 4‑13: Revision Control
CODE |
DESCRIPTION |
REVISION |
Work In Progress (WIP) |
||
S0 |
InitialStatus |
Preliminary revision and version |
Shared (non-contractual) |
||
S1 |
Suitable for coordination |
Preliminary revision |
S2 |
Suitable for information |
Preliminary revision |
S3 |
Suitable for review and comment |
Preliminary revision |
S4 |
Suitable for stage approval |
Preliminary revision |
S5 |
Withdrawn* |
N/A |
S6 |
Suitable for PIM authorization |
Preliminary revision |
S7 |
Suitable for AIM authorization |
Preliminary revision |
Published (contractual) |
||
A1,... An |
Authorized and accepted |
Contractual revision |
B1,... Bn |
Partial sign-off (with comments) |
Preliminary revision |
Published (for AIM
acceptance) |
||
CR |
As constructed record document |
Contractual revision |
Table 4‑14:
Status codes for information
containers within the CDE
CONTAINER |
METADATA |
||||||
INFORMATION |
DESCRIPTION |
STATUS |
REV. |
AUTHOR |
SUBMITTAL |
CONTAINER
CLASSIFICATION |
|
CONTAINER
NAME |
DATE |
CODE |
DESCRIPTION |
||||
XXXXXX-XXX-XXXX-XXXX-XX-XXX-XX-XXXXXXX |
************ |
XX |
XXX.XX |
******* |
DD/MM/YY |
************ |
************ |
Table 4‑15: Metadata
Assignment
Code |
APPLICATION OF STATUS CODES |
DESCRIPTION |
|
S0 |
Assigned by task
teams to identify information containers as Work in Progress and not yet
suitable to be Shared |
S1 |
Assigned by task
teams to limit the information container’s use to coordination activities
only by its recipients. |
S2 |
Assigned by task
teams to limit the information container`s use for any specific activity by
its recipients. This status |
S3 |
Assigned by task
teams to limit the information container`s use to commenting and review activities
only by its |
S4 |
Assigned by task
teams to limit the information container`s use to stage approval activities
only by its recipients. The |
S5 |
This status code
is not used in the National Annex |
S6 |
Assigned by task
teams to limit the information container`s use to the lead appointed party’s
authorization of the project information model (see ISO 19650-2 clauses 5.7.1
and 5.7.2). The information should not be used for contractual purposes, for
example, construction until the project information model that it forms part
of has been |
S7 |
Assigned by task
teams to limit the information container`s use to authorization activities
for Stage 6 (Handover) only |
A0 |
Assigned by task
teams to represent the Stage the authorized and accepted information
container relates to in |
CR |
Assigned by task teams to represent an information container that has
been authorized and accepted and was |
Table 4‑16: Application of Status Codes
Ø All information exchanges will be generated according to "Common Data Environment standards, methods and procedures".
Ø All information exchanges will follow Information Delivery Manual.
MODEL
DESCRIPTION DOCUMENT (MDD:) During exchanging
models Model Description Document (MDD) has to be maintained by each
discipline.
þ At official publishing points, the publisher is responsible for the consequences caused by incomplete or incorrect documentation.
þ Please find the template of MDD to be filled by each responsible party below:
MODEL DESCRIPTION
DOCUMENT (MDD) |
|
DOCUMENT NO |
|
DISCIPLINE |
|
PROJECT NAME |
|
BEP REFERENCE & REVISION |
|
AGREED MODEL USE |
The model has been issued for ... |
MODEL AUTHORING COMPANY |
|
DISCIPLINE BIM LEAD |
|
NATIVE FILE TYPE & VERSION |
(e.g. Revit 2020) |
ISSUED FILE TYPE & VERSION |
(e.g. Navisworks 2020) |
UNITS & MEASUREMENT |
|
COORDINATE SYSTEM |
|
ISSUED DATE |
|
MODEL STATUS |
|
MODEL NAME |
|
FILE NAME |
|
LINKED FILES |
|
DATA CONTENT OF THE MODEL |
|
INPUTS |
|
MODEL PURPOSE |
|
CHANGES & UPDATES |
|
AREAS ON HOLD |
|
COMMENTS |
|
Table 4‑17: Model Description Document Template
.....
FILE TYPE |
DESCRIPTION |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 4‑18: Exchange Formats Table
? Describe the standards of attribute data ( parameters, shared parameters, discipline special parameters, URL Data, Spatial Data, Cobie Data, Classification Number etc.) and how to use them. Describe how to use the Attribute Data Log.
.....
Ú Refer to: (under folder: Delivery_IMDocs/BEP)
Annex_4.1 = ATD: Attribute Data Log
? The minimum COBie attributes for typical BIM
will be defined in below table and standards for COBie usage in the project
will be mentioned.
.....
Attribute /Parameter |
Data Type |
Description |
Responsible Party |
COBie-Floor-Category |
TEXT |
Category
of the floor (Site, Floor, Roof). |
Design
team |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 4‑19: COBie DATA
COBie Sheet |
Classification
Table |
Contact |
|
Facility |
|
Space |
|
Type |
|
System |
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 4‑20: Classification and COBie
....
ASSET NAME |
DESCRIPTION |
PIM |
AIM |
||
INCLUDED |
EXCLUDED |
INCLUDED |
EXCLUDED |
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 4‑21: Information to
be excluded from or included in information models table
? Describe the standards for IFC & MVD to be used in the project.
.....
IFC VERSION |
BIM USE |
IFC 2x3 |
Design Authoring |
IFC 4 |
..... |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 4‑22: Project's IFC
Standards Table
MVD VERSION |
BIM USE |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 4‑23: Main MVDs of The Project
.....
Figure 4‑1: Process Map - Exchange of Information Between within the Apop's Organization
.....
Figure 4‑2: Process Map - Exchange of
Information Between the Apop and External Stakeholders
.....
Figure 4‑3: Process Map - Exchange of
Information Between Apop and External Operators or Maintainers
.....
Figure 4‑4: Process Map - Exchange of Information Between Peap and the App
.....
Figure 4‑5: Process Map - Exchange of Information Between PEAPs on the Same Project
.....
Figure 4‑6: Process Map - Exchange of
Information Between Independent Projects
I
Ref.to ISO-19650-2/5.1.4.c
.....
Ú
Refer to:
Annex_7.1 = HLRM_1: Delivery team’s High Level Responsibility
Matrix
Annex_7.2 = DRM_0: Delivery Team’s Detailed Responsibility Matrix
(Initial/Template)
Table 4‑24: Method of assignment for Level of Information Need Table
.....
I The project team should agree common units
of measurement.
.....
TYPE OF INFORMATION |
Millimeters |
Meters |
Degrees |
Radians |
Clockwise |
Counter- Clockwise |
SURVEY |
|
|
|
|
|
|
Models-ARCHITECTURE |
|
|
|
|
|
|
Models-STRUCTURE |
|
|
|
|
|
|
Models-MECHANICAL & PLUMBING |
|
|
|
|
|
|
Models-ELECTRICAL |
|
|
|
|
|
|
Models-LANDSCAPE |
|
|
|
|
|
|
Models-Discipline X1 |
|
|
|
|
|
|
Models-Discipline X2 |
|
|
|
|
|
|
Drawings-ARCHITECTURE |
|
|
|
|
|
|
Drawings-STRUCTURE |
|
|
|
|
|
|
Drawings-MECHANICAL & PLUMBING |
|
|
|
|
|
|
Drawings-ELECTRICAL |
|
|
|
|
|
|
Drawings-LANDSCAPE |
|
|
|
|
|
|
Drawings-Discipline X1 |
|
|
|
|
|
|
Drawings-Discipline X2 |
|
|
|
|
|
|
XX |
|
|
|
|
|
|
Table 4‑25: Units and Measurement
? Coordinate System type will be mentioned. Origin
and other spatial coordination related items will be given in the 5th Chapter.
.....
I
Ref.to ISO-19650-2/5.2.1.b/Note
I
Agreed Construction Tolerances for all Disciplines
.....
PHASE |
DISCIPLINE |
TOLERANCE / DESCRIPTION |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 4‑26: Level of Accuracy Table (LOA)
?
Mention sheet sizes to be used in the project and describe
the sheet organization of the project.
?
Describe the templates and title blocks to be used in the
project.
.....
.....
Table 4‑27: Sheet Sizes
.....
.....
.....
.....
.....
.....
.....
.....
I
Explain the agreed modelling & publishing standards of
the Project's organization (such as User Interface, Setting Stories/Levels, Detailing
etc.)
.....
.....
? Explain the agreed publishing standards of the Project's organization
? Information to be either excluded from or included in information models when publishing.
.....
? Ref.to ISO-19650-2/5.1.4.d, 5.8.1:
.....
.....
(ref.to
ISO-19650-2/5.4.1: confirm and document the
delivery team’s proposed
information production methods
and procedures)
Ú Documents:
4
QUA: Quality Assurance, Coordination & Issue Management
Manual
4
DAS: Data Segregation
4
SCO: Spatial Coordination (Coordinates) Methods & Procedures
4
SCR: Security Requirements
4
PAT-MP: PIM to AIM Transition Methods and Procedures (Ref.to
5.8.1)
4
CDM: CDM/Health & Safety Requirements
4
COL-PP: Collaboration Process & Procedures (within the
CDE)
4
CDE-SMP_1: Project's CDE Structure, Standards,
Methods, Procedures
4
OIR: Organizational Information Requirements
4
PIR: Project Information Requirements
4
REM-A_1: Information Management Assignment Matrix
4
PMP_1: Project's Information Production Methods and
Procedures
4
PRS_1: Procurement Route (Schema & Table)
.....
Table 5‑1: Coordinates and Geo-Location Table (SCO)
.....
Figure 5‑1: PIM Origin
& Orientation
I
Ref. to. ISO 19650-2/5.3.2,
5.4.1
I
Including any agreed
changes from "Tender Response" Package.
?
Mention federation strategy
and information container breakdown structure with tables, figures such as
below and necessary explanations such as linking strategies.
.....
FEDERATION PARTS LIST |
||||||||
LEVEL 1 |
LEVEL 2 |
LEVEL 3 FEDERATION PARTS |
FLOOR |
DESCRIPTION |
||||
Sub Division |
Stair |
Structural |
Mechanical |
Electrical |
||||
Table 5‑2:Federation Parts List (Sample)
Figure 5‑2: Information
Container Breakdown of the Federation Strategy
I
Ref. to. ISO 19650-2/5.3.2
.....
.....
SURVEY METHOD |
DELIVERY FORMAT |
SURVEY ORIGIN |
NOTES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 5‑3: Survey Strategy
.....
Figure 5‑3: Quantity extraction & tracking strategy
I
Please refer to Project's Common Data Environment standards,
methods & procedures mentioned in Chapter 3.3.
.....
.....
Table 5‑4: Security &
Extranet Access, Distribution
Authority
I
Please refer to Chapter 3.for CDE
I
Please refer to Chapter 4.for Project's Modelling Standards.
I
Please refer to Chapter 4.for Project's Publishing Standards.
....
?
Collaboration (including Modelling Process Management & Publishing) strategy should be defined
according to "Federation strategy & information container breakdown
structure" and "Common Data Environment Rules" described above.
....
.....
?
Modelling Process/Workflow should be defined with rules,
procedures & methods to be followed.
....
Figure 5‑4: Modelling Process/Workflow Schema
? Mention the methods and procedures of usage of IFC and MVD in the project.
....
I
As part of planning BIM data exchange methodologies it is
beneficial to test the exchange workflows prior to commencing the project
models. This process is helping to establish the most efficient ways of
collaboratively exchanging information as well as reducing the risk of problems
later in the process.
?
Before each phase exchange workflows (including all Bim Uses
which will be used in that phase) must be tested to establish the most
efficient ways of collaboratively exchanging information as well as reducing
the risk of problems later in the processes. These tests are recorded in below
table.
....
Test Mock-Up No |
PHASE |
BIM USE (as code, ref. to
Annex-3.3) |
RESULT (Ok/Not OK Ok with notes) |
COMMENT |
01 |
|
|
|
|
02 |
|
|
|
|
03 |
|
|
|
|
04 |
|
|
|
|
05 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 5‑5: BIM Test Mock-Ups Table
.....
? Mention the electronic communication procedures with taking CDE into consideration.
....
? Mention the meeting communication procedures with taking CDE into consideration.
....
MEETING SCHEDULE |
||
MEETING TYPE |
FREQUENCY |
PARTICIPANTS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 5‑6: Meeting Schedule
.....
? Mention "Change
Log" procedures.
Ú
Refer to (under folder: Delivery_IMDocs/BEP)
Annex_5.1 = CHL: Change Log Template
.....
? Agreed "Data
Management System" according to "Federation Strategy",
"Information container naming requirements (ICN)" and above related
sub-chapters should be defined.
....
.....
.....
.....
.....
.....
Ú Refer to (under folder: Delivery_IMDocs/BEP)
Annex_5.2 = CLAM: Clash Detection Matrix
.....
.....
.....
I
Ref. to. ISO 19650-2/5.1.5,
5.3.2,
.....
I Ref.to ISO-19650-2/5.4.1: update the
delivery team’s information delivery strategy (as required))
I Including any agreed changes from "Invitation
to Tender" Package. Ref. to ISO 19650-2/5.1, 5.2
I
Including
any agreed changes from "Tender Response" Package. Ref. to ISO
19650-2/5.3
Ú Documents:
4 EIR_APOP: Appointing Party's Exchange Information Requirements
4 ACR: Acceptance Criteria Manual
4 CCA_IM: Information Management Capability and Capacity
Assessment Form
4 CCA_IP: Information Production Capability and Capacity
Assessment Form
4 CCA_IT: Information Technology
Capability and Capacity Assessment Form
4 RAS_1: Risk Assessment Requirements
? The following areas of BIM implementation
should be considered and included in appointments where applicable:
: Model Development and Responsibilities of
Parties Involved ; Model Sharing and Reliance; Interoperability; Model
Management; Intellectual Property Rights
? Appointment documents (templates &
attachments which are addressing the BIM implementation of the project) to be
followed (during the first appointment:
Project's Information Protocol
Examples for Appointment documents:
X
CIC Documents
X
AIA Document C106 - 2013: Digital Data Licensing Agreement.
X
AIA Document G201 - 2013: Project Digital Data Protocol Form
X
AIA Document G202 - 2013: Project Building Information Modeling Protocol
Form
X
AIA Document E201 - 2007: Digital Data Protocol Exhibit
X
AIA Document E202 - 2008: BIM Protocol Exhibit. This document
addresses the development of a model throughout a project.
X
AIA Document E203 - 2013: Building Information Modeling and Digital
Data Exhibit
X
AIA Document B101 - 2007: Standard Form of Agreement Between Owner and
Architect
X
AIA Document A101 - 2007: Agreement Between Owner and Contractor
X
AIA Document B195 - 2008: An Owner-Architect agreement
X
AIA Document A195 - 2008: A Guaranteed Maximum Price (GMP) Owner and
Contractor Agreement
X
AIA Document A295 - 2008: General Conditions of the Agreement for
Integrated Project Delivery
X AIA Document B207 - 2008: On-Site Project
Representation scope of services document
X AIA Document C195 - 2008: Standard Form
Single Purpose Entity
X AIA Document C196 - 2008: The agreement
between the SPE and the project owner
X AIA Document C197 - 2008: The agreement
between the SPE and any non-owner SPE member.
X Consensus DOCS 301 BIM Addendum. This
document addresses the risk management of a BIM design process.
X Consensus DOCS 200.2: Electronic
Communications Protocol Addendum
? Appointment documents (templates &
attachments which are addressing the BIM implementation of the project) to be
followed will be mentioned including the authority (RACI) to check the
appointment during deliverables (such as Lead Designer's Project Manager etc.). Appointment documents related
requirements specific for BEP will be mentioned.
.....
APPOINTMENT DOCUMENT NAME |
AUTHORITY (mentioned
with the codes of the actors/parties) |
|||
R |
A |
C |
I |
|
INP_1: Project's Information
Protocol |
|
|
|
|
AIA
Document - A295–2008: For general |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 6‑1: Appointment Document RACI Table
....
Ø Please refer to ISO-19650-2/5.1.8, 5.2.1,
5.2.3, 5.3.4, 5.3.6, 5.3.7
? Mention the updated Risk
Assessment Requirements (to guide risk management through whole life cycle of
the project).
? Mention the Key Performance
Indicators
.....
.....
KPI NAME |
DESCRIPTION |
RESULT OF KPI (0=Ineffective,
1=Less, 2= Effective, 3=Strongly Effective, 4= Most Effective, a=Pass/Reasonable, b=Not Pass/Unreasonable) |
Reduce implementation cost |
Clash detection frequency |
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 6‑2: (KPIS) Key Performance Indicators
Ø Please refer to ISO-19650-2/5.2.1, 5.2.3,
5.4.3, 5.6.5
Annex_6.1 = ACR_1:
Acceptance Criteria Manual
þ
Document
Location: " ACR_1
" is under folder: Delivery_IMDocs/BEP
? For further details of
Acceptance Criteria for both submission and approval processes (for LEAP, APP
and all Task Teams) update the ACR and give as annex of this BEP. Refer to
ACR_1 document throughout the whole Life Cycle.
? Mention how to use the
ACR_1 document.
.....
Ø Please refer to ISO-19650-2/5.3.3
? Describe the report of updated task teams' capability and capacity
with referring to 6.3.1 and 6.3.2
? This report will be checked and updated (if
necessary) before each Bim Use and Main Phase begins
.....
Ø Please refer to ISO-19650-2/5.3.3
? Describe the result of updated task teams' capability and capacity
assessments.
? Task teams' capability and capacity
assessments should be checked before each Bim Use and Main Phase begins by the
Lead Appointed Party with using below forms (ref.to 6.3.1.1, 6.3.1.2, 6.3.1.3)
.....
Ø Please refer to ISO-19650-2/5.3.3, and;
Annex_6.2 = CCA_IM:
Information Management Capability and Capacity Assessment Form
þ Document Location: " CCA_IM " is under folder: Delivery_IMDocs/BEP
? Mention methods to use this
form for capability and capacity assessment of task teams.
.....
Ø Please refer to ISO-19650-2/5.3.3, and;
Annex_6.3 = CCA_IP: Information Production Capability and Capacity Assessment Form
þ Document Location: " CCA_IP " is under folder: Delivery_IMDocs/BEP
? Mention methods to use this
form for capability and capacity assessment of task teams.
.....
Ø Please refer to ISO-19650-2/5.3.3, and;
Annex_6.4 = CCA_IT:
Information Technology Capability and
Capacity Assessment Form
þ Document Location: " CCA_IT " is under folder: Delivery_IMDocs/BEP
? Mention methods to use this
form for capability and capacity assessment of task teams.
.....
Ø Please refer to ISO-19650-2/5.3.3
?
Mention task
teams' updated information delivery strategies.
?
Task teams' information delivery strategies need to be
considered and evaluated before each "Bim Use" or "Main
Phase" begins. According to the evaluation necessary revisions must be
requested and coordinated.
.....
Ø Please refer to ISO-19650-2/5.3.4
?
Mention the
delivery teams' updated capability and capacity.
?
Delivery team’s capability and capacity needs to be considered
and evaluated before each "Bim Use" or "Main Phase" begins.
According to the evaluation necessary precautions (trainings etc.) must be
taken.
.....
Ø Please refer to ISO-19650-2/5.3.5, 5.5.1,
5.5.2, 5.5.3, and;
Appendix_6.5 = MOB_1:
DELIVERY TEAM'S MOBILIZATION PLAN
þ Document Location: "MOB_1" is under folder: Delivery_IMDocs
?
Update Delivery
Team's Mobilization Plan according to 6.1 ,6. 2 and 6.3
?
Mention main
objectives of the Delivery Team's Mobilization Plan and refer to MOB for
further details.
.....
Ø Please refer to ISO-19650-2/5.3.6
? Describe the updated delivery team's risk register.
?
According to the analysis of the finalized activities and
lessons learned during each activity, "Delivery Team’s Risk Register"
needs to be updated after each activity ends.
.....
I
Ref.to
ISO-19650-2/5.3.2.b: containing
·
the delivery team’s approach to meeting the appointing
party’s exchange information requirements,
·
a set of objectives/goals for the collaborative
production of information,
·
an overview of the delivery team’s organizational
structure and commercial relationships, and
·
an overview of the delivery team’s composition, in the
form of one or more task teams;
I
Ref.to
ISO-19650-2/5.4.1.b: update the delivery team’s information delivery strategy (as required);
?
Explain
the "Updated Information Delivery Strategy" with referring to IDM and
6.1-6.6 Sub-Chapters:
þ Approach to meeting
the appointing party’s EIR
þ Collaborative
Production of Information Objectives/Goals
þ Delivery Team's
Organizational Structure
þ
Delivery Team’s Composition,
.....
? Short brief summary of "Project's IDM". Refer to "Project's
IDM" for further details.
.....
Figure 6‑1: Project's Brief Process Map
Appendix_6.6 = IDM: INFORMATION DELIVERY MANUAL
I Ref.to ISO-19650-2/5.3.2: "The delivery
team’s high-level responsibility matrix contains the allocated responsibility for
each element of the information model and the key deliverables associated to
each element."
I Ref.to ISO-19650-2/5.4.1: "Update the
delivery team’s high-level responsibility matrix (as required). "
I Ref.to ISO-19650-1/3.1.1: responsibility matrix:
chart that describes the participation by various functions in completing tasks or deliverables [SOURCE:
ISO 37500:2014,
3.16 – modified]. Note
1 to entry: A responsibility matrix can indicate accountability, consultation and informing, alongside the obligation to complete tasks or deliverables.
I Ref.to ISO-19650-1/10.3: A responsibility matrix should be generated as part of the information delivery planning process in one or more levels of detail. The axes of a responsibility matrix
should identify:
·
information management functions; and
·
either project or asset information management tasks, or information deliverables as appropriate.
The content of a responsibility matrix
should show the appropriate detail relevant to the axes.
Ú Please refer to (under
folder:
Delivery_IMDocs/BEP);
Annex_7.1 = HLRM_1: Delivery team’s High Level Responsibility Matrix
Please kindly find the High Level Responsibility Matrix of the project attached to this document.
.....
?
Ref.to ISO-19650-2/5.4.2: The lead appointed party shall
further refine the high level responsibility matrix to establish the detailed
responsibility matrix, which identifies:
·
what information is to be produced;
·
when the information is to be exchanged
and with whom; and
·
which
task team is responsible
for its production.
Ø
In doing this, the lead appointed party shall consider:
o
the information delivery
milestones; the high level responsibility matrix; the project’s information
production methods and procedures; the elements of information container
breakdown structure allocated to each task team; and the dependencies on the
information production process.
?
Details (how to use, structure etc.) of "Delivery Team's
Detailed Responsibility Matrix" will be given. Template/Initial Work will be given in the first BEP and afterwards
during each revision the up-to-date Detailed Responsibility Matrix will be
given as Annex of the BEP. Detailed Responsibility Matrix is also including the
BIM Uses parameter.
Ú Please refer to (under
folder:
Delivery_IMDocs/BEP);
Annex_7.2 = DRM_0: Delivery Team’s Detailed Responsibility Matrix Initial Version (Template)
Please kindly find the Detailed Responsibility Matrix Template of the project attached to this document.
.....
?
Ref.to
ISO-19650-2/3.1.3.4: task information delivery plan (TIDP) schedule of
information containers and delivery dates, for a specific task team.
?
Ref.to
ISO-19650-2/5.4.4: Each task team shall establish, and maintain throughout its
appointment, a task information delivery plan (TIDP). In doing this, each task
team shall consider:
·
the project’s information delivery milestones;
·
the task team’s responsibilities within the detailed responsibility
matrix;
·
the lead appointed party’s information requirements;
·
the availability of shared resources within the delivery team; and
·
the time the task team will need to produce (generate,
coordinate, review and approve) information
The
TIDP shall list and identify, for each container, the:
·
name and title;
·
predecessors or dependencies;
·
level of information need;
·
the (estimated) production duration;
·
information author responsible for its production; and
·
delivery milestones.
?
Task
Information Delivery Plan Template should be explained (how to use, content
etc.).
Ú Please refer to (under
folder:
Delivery_IMDocs/BEP);
Annex_7.3 = TIDP-TMP: Task Information Delivery Plan Template
Please kindly find the Task Information Delivery Plan Template of the project attached to this document.
.....
I
Ref.to ISO-19650-2 / 3.1.3.3: master information delivery plan_MIDP_plan
incorporating all relevant task information delivery plans
I
Ref.to ISO-19650-2 / 5.4.5: The lead appointed party shall
aggregate the TIDP from each task team in order to establish the delivery
team’s master information delivery plan (MIDP). In doing this, the lead
appointed party shall consider:
the assigned responsibilities within the detailed
responsibility matrix; the information predecessors or dependencies on
information between task teams; the time the lead appointed party will need to
review and authorize the information model; and the time the appointing party
will need to review and accept the information model.
Once the MIDP
has been established, the lead appointed party shall:
baseline the deliverables and dates within the MIDP; inform
each task team and notify if any changes are required to the TIDP; and inform
the appointing party of any risks or issues which could impact on the project’s
information delivery milestones.
I
ISO 19650-1/6.3.4: If new parties join the delivery team, the
delivery plan should be updated to include and confirm the information they
will be contributing to future information exchanges.
?
Initial version of Master Information Delivery Plan will be presented.
How to use etc. instructions will be given.
Ú Please refer to (under
folder:
Delivery_IMDocs/BEP);
Annex_7.4 = MIDP_0: Master Information Delivery Plan Initial Version (Template)
Please kindly find the Master Information Delivery Plan Initial Version (Template) of the project attached to this document.
I
Ref.to
ISO-19650-2 / 5.3.2.g: ..Include a proposed schedule of software (including
versions), hardware and IT infrastructure the delivery team intend to adopt.
I
Ref.to
ISO-19650-2 / 5.3.5.f: ...The delivery team's mobilization plan will be
established with considering PEAP's approach, timescales and responsibilities
for procuring,
implementing, configuring and testing additional software, hardware and IT infrastructure;
I
Ref.to
ISO-19650-2 / 5.4.1.f : ...confirm the schedule of software, hardware and IT
infrastructure the delivery team will use.
I
Ref.to
ISO-19650-2 / 5.5.2.a: ...procure, implement, configure and test software,
hardware and IT infrastructure (as required);
?
Requirements to be followed during "Software
Selection" process (for to follow during further updates, revisions), process
& data management systems, Common Data Environment related instruction.
Ä Note: Please refer to Table
8.1 for the whole schedule.
.....
?
Requirements to be followed during "Hardware Selection"
process (for to follow during further updates, revisions).
?
Requirements to be followed during "IT
Infrastructure" process (for to follow during further updates, revisions).
Ä Note: Please refer to Table
8.1 for the whole schedule.
.....
SOFTWARE |
||||
SOFTWARE
NAME |
SOFTWARE'S
SCOPE |
VERSION |
NATIVE
FILE |
BIM
USE CODE(S) (Ref.to.
Bim Uses Desc.&Del.Table) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
HARDWARE |
||||
HARDWARE NAME |
DESCRIPTION |
BIM
USE CODE(S) |
||
|
|
|
||
|
|
|
||
IT INFRASTRUCTURE |
||||
NAME |
DESCRIPTION
/ SCOPE |
VERSION |
BIM
USE CODE(S) |
|
ENTERPRISE SOTWARE
APPLICATIONS |
||||
|
|
|
|
|
COMPUTER HARDWARE
PLATFORMS |
||||
|
|
|
|
|
CONSULTANTS &
SYSTEM INTEGRATORS |
||||
|
|
|
|
|
NETWORKING /
TELECOMMUNICATIONS |
||||
|
|
|
|
|
DATA MANAGEMENT
& STORAGE |
||||
|
|
|
|
|
OPERATING SYSTEM
PLATFORMS |
||||
|
|
|
|
|
INTERNET PLATFORMS |
||||
|
|
|
|
Table 8‑1: (SCH-IT_1)
Schedule of Software, Hardware & IT
I The templates which will be used during further delivery phase activities are mentioned below. These documents are part of the "Project Package" and mentioned in this BEP as a guide for to use during the related activity. Please kindly find the location information for these documents below.
Ø Please refer to
ISO-19650-2/5.4.3. and;
Appendix_9.1 = EIR-LEAP-TMP: Lead Appointed Party's Exchange Information Requirements Template
þ Document Location:
"EIR-LEAP" is under folder: Delivery_IMDocs
Ä Delivery_IMDocs=Delivery Phase Information Management Documents
þ Template Location:
"EIR-LEAP-TMP" is under folder: Shared_Resources / Delivery _Activities / Templates
Ø Please refer to
ISO-19650-2/5.5.1 and;
Appendix_9.2 = MORE-TMP: Mobilization of Resources Report Template
þ Document Location:
"MORE" is under older: Delivery_IMDocs
þ Template Location:
"MORE-TMP" is under folder: Shared_Resources / Delivery _Activities / Templates
Ø
Please refer to ISO-19650-2/5.5.2 and;
Appendix_9.3 = MOIR-TMP: Mobilization of Information Technology Report Template
þ Document Location:
"MOIR" is under folder: Delivery_IMDocs
þ Template Location:
"MOIR-TMP" is under folder: Shared_Resources / Delivery _Activities / Templates
Ø
Please refer to ISO-19650-2/5.5.3 and;
Appendix_9.4 = PMP-RR-TMP:
Project's Information Production Methods and Procedures Test Report Template
þ Document Location:
"PMP-RR" is under folder: Delivery_IMDocs
þ Template Location:
"PMP-RR-TMP" is under folder: Shared_Resources / Delivery _Activities / Templates
Ø Please refer to ISO-19650-2/5.6.1 and;
Appendix_9.5 = CR-TT-TMP: Task Team's Access Check Report Template
þ Document Location:
"CR-TT" is under folder: Delivery_IMDocs
þ Template Location:
"CR-TT-TMP" is under folder: Shared_Resources / Delivery _Activities / Templates
Ø Please refer to ISO-19650-2/5.6.3
and;
Appendix_9.6 = QUA-TT-TMP: Task Team's Quality Assurance Check Report Template
þ Document Location:
"QUA-TT" is under folder: Delivery_IMDocs
þ Template Location:
"QUA-TT-TMP" is under folder: Shared_Resources / Delivery _Activities / Templates
Ø Please refer to ISO-19650-2/5.6.4
and;
Appendix_9.7 = IRR-TT-TMP: Task Team's Information Review (by Task Team) Report Template
þ Document Location:
"IRR-TT" is under folder: Delivery_IMDocs
þ Template Location:
"IRR-TT-TMP" is under folder: Shared_Resources / Delivery _Activities / Templates
Ø Please refer to ISO-19650-2/5.6.5
and;
Appendix_9.8 = IMR-DT-TMP: Delivery Team's Information Model Review Report Template
þ Document Location:
"IMR-DT" is under folder: Delivery_IMDocs
þ Template Location:
"IMR-DT-TMP" is under folder: Shared_Resources / Delivery _Activities / Templates
Ø Please refer to ISO-19650-2/5.7.2
and;
Appendix_9.9 = TTS-RR-TMP: Task Teams' Submittals & PIM Review Report by Leap Template
þ Document Location:
"TTS-RR" is under folder: Delivery_IMDocs
þ Template Location:
"TTS-RR-TMP" is under folder: Shared_Resources / Delivery _Activities / Templates
Ø Please refer to
ISO-19650-2/5.7.1 & 5.7.3 and;
Appendix_9.10 = SBL-TMP: Submittal Lists Template
þ Document Location:
"SBL" is under folder: Delivery_IMDocs
þ Template Location:
"SBL-TMP" is under folder: Shared_Resources / Delivery _Activities / Templates
Ø Please refer to
ISO-19650-2/5.7.4 and;
Appendix_9.11 = PIM-RR-TMP: Appointing Party's PIM Review Report Template
þ Document Location:
"PIM-RR" is under folder: Delivery_IMDocs
þ Template Location:
"PIM-RR-TMP" is under folder: Shared_Resources / Delivery _Activities / Templates
Ø Please refer to
ISO-19650-2/5.8.1 and;
Appendix_9.12 = PAR-TMP: PIM to AIM Requirements Template
þ Document Location:
"PAR" is under folder: Delivery_IMDocs
þ Template Location:
"PAR-TMP" is under folder: Shared_Resources / Delivery _Activities / Templates
Ø In collaboration with each lead appointed party, the appointing party shall capture lessons learned during the project and record them in a suitable knowledge store, to be called upon by future projects.
Ø Please refer to ISO-19650-2/5.8.2 and;
Appendix_9.13 = CLL-TMP: Capture Lessons Learned Template (for LEAP and APP's Use)
Appendix_9.14 = RLL-TMP: Lessons Learned Register Template(by APOP)
þ Document Location:
"CLL & RLL" are under folder: Delivery_IMDocs
þ Template Location:
"CLL-TMP & RLL-TMP" are under folder: Shared_Resources / Delivery _Activities / Templates
I Templates as per ISO 19650-3 activities will be produced during PIM to AIM process (the beginning of Operational Phase) and as explained in the Operational Phase BEP .
þ Documents Location:
are under folder: Operational_IMDocs
Ä Operational_IMDocs=Operational Phase Information Management Documents
þ Templates Location:
are under folder: Shared_Resources / Operational _Activities / Templates
: The following documents are listed for reference.
1. ISO 19650-1: Organization
and digitization of information about buildings and civil engineering works,
including building information modelling (BIM) — Information management using
building information modelling — Part 1: Concepts and principles
2. ISO 19650-2: Organization
and digitization of information about buildings and civil engineering works,
including building information modelling (BIM) — Information management using
building information modelling — Part 2:Delivery phase of the assets
3. ISO_PD-19650-0-2019:
Transition guidance to BS EN ISO 19650
4. ISO 29481-1:2016=Building
information models-Information delivery manual-Part 1: Methodology and format
5. ISO 29481-2:2012=Building
information models-Information delivery manual-Part 2:Interaction framework
6. IS/ISO 13567-1 :
1998=Technical product documentation —Organization and naming of layers for CAD
PART 1 OVERVIEW AND PRINCIPLES
7. ISO/TR 13567-3 : TECHNICAL
REPORT Technical product documentation —Organization and naming of layers for
CAD Part 3: Application of ISO 13567-1 and ISO 13567-2
8. ISO 7200: Technical
product documentation — Data fields in title blocks and document headers
9. ISO 12006-2:2015 Building
construction —Organization of information about construction works Part 2:
Framework for classification
10. ISO 12006-3-2007 Building
construction — Organization of information about construction works Part 3:
Framework for object-oriented information
11. ISO 22263:2008:
Organization of information about construction works -Framework for management
of project information
12. ISO TS 12911-2012
Technical Specification-Framework for building information modelling (BIM)
guidance
13. BSI_PAS 1192-3:2014=
Specification for information management for the operational phase of assets
using building information modelling
14. BS 1192-4:2014
=Collaborative production of information (Part 4: Fulfilling employer’s
information exchange requirements using COBie – Code of practice)
15. BSI_PAS_1192_5:2015=Specification
for security-minded building information modelling, digital built
environments
and smart asset management.
16. BSI_PAS_1192_6:2018=Specification
for collaborative sharing and use of structured Health and Safety information
using BIM
17. BS 8541-1, 2, 3, 4; 5, 6:
Library objects for architecture, engineering and construction
18. BS 8536-1:2015=Briefing
for design and construction –Part 1: Code of practice for facilities management
(Buildings infrastructure)
19. BS 8536-2= Briefing for
design and construction –Part 2: Code of practice for asset management (Linear
and geographical infrastructure)